PRJ-2026-018At risk4ExecutionConstruction

Secure Enterprise Network

Add to watchlist

Fibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 132M

Actual cost

SAR 74.8M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 136.1M

SAR +4.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−9

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦52%⁩ chance of a further slip within ⁦45⁩ days

From the SPI trend (⁦0.87⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦55%⁩ done against ⁦63%⁩ planned.

SPI ⁦0.87⁩, CPI ⁦0.97⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Leading, Sustainable OrganisationSO-4.1Strong technical capabilities

Main initiative

SI-3.3.1Smart centres

Contribution to the initiative⁦36%⁩

The project’s share of the initiative’s project budget (4 projects)

Secondary links

Annual work-plan line
WP-2025-018
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦55%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦35%⁩

6 deliverables accepted

  • Site works & excavation⁦16%⁩
  • Structure⁦16%⁩
  • Detailed design⁦8%⁩
  • Permits & approvals⁦7%⁩
  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Finishes⁦10%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦89%⁩ of budget

74.8M/ 132M4.1Mprojected overrun(⁦3.1%⁩)
Actual spend
74.8M
Committed
118M
Approved budget
132M
Estimate at completion
136.1M

Next milestones

  • Provisional acceptance⁦2027-01-06⁩was ⁦2026-12-12⁩Late
  • Closure⁦2027-03-05⁩was ⁦2027-01-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Risks & impediments

2 open risks, exposure SAR 6.1M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩1Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩RSK-0033Municipal objections to trenching in built-up districtsProbability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0032Higher reinstatement costs after network trenchingProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium2
  • Low0

Deliverables

⁦6⁩ of ⁦12⁩ approved

  • Project plan & baseline018-D1 · V1 · CRT-018-01⁦4%⁩Eng. Omar H. Bawazir⁦2025-07-30⁩2025-07-305 Safar 1447 AHApproved
  • Monitoring & reporting018-D2 · V1 · CRT-018-02⁦4%⁩Eng. Nayef H. Al-Buqami⁦2025-09-18⁩2025-09-1826 Rabiʻ I 1447 AHApproved
  • Detailed design018-D3 · V1 · CRT-018-03⁦8%⁩Eng. Nayef H. Al-Buqami⁦2025-11-07⁩2025-11-0716 Jumada I 1447 AHApproved
  • Permits & approvals018-D4 · V1 · CRT-018-04⁦7%⁩Eng. Majed S. Al-Rasheed⁦2025-12-27⁩2025-12-277 Rajab 1447 AHApproved
  • Site works & excavation018-D5 · V1 · CRT-018-05⁦16%⁩Eng. Majed S. Al-Rasheed⁦2026-02-15⁩2026-02-1527 Shaʻban 1447 AHApproved
  • Structure018-D6 · V1 · CRT-018-06⁦16%⁩Eng. Omar H. Bawazir⁦2026-04-06⁩2026-04-0618 Shawwal 1447 AHApproved
  • Finishes018-D7 · V1⁦10%⁩Eng. Nayef H. Al-Buqami155 days overdue2026-05-269 Dhuʻl-Hijjah 1447 AHIn review
  • Supply018-D8 · V0⁦8%⁩Eng. Omar H. Bawazir105 days overdue2026-07-151 Safar 1448 AHDraft
  • Installation018-D9 · V0⁦8%⁩Eng. Nayef H. Al-Buqami55 days overdue2026-09-0321 Rabiʻ I 1448 AHDraft
  • Testing & commissioning018-D10 · V0⁦8%⁩Eng. Majed S. Al-Rasheed5 days overdue2026-10-2312 Jumada I 1448 AHDraft
  • Provisional acceptance018-D11 · V0⁦6%⁩Eng. Nayef H. Al-BuqamiIn 45 days2026-12-123 Rajab 1448 AHDraft
  • Final acceptance018-D12 · V0⁦5%⁩Eng. Majed S. Al-RasheedIn 95 days2027-01-3123 Shaʻban 1448 AHDraft

Team, contracts & documents

Team

1 member

Eng. Omar H. Bawazir · Director, IT Infrastructure
  • Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureProject managerP-024o.bawazir@sca.sa⁦35%⁩