Secure Enterprise Network
Add to watchlistFibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
SAR +4.1M
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure12 December 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
Fibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.
In scope
- Fibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.
- Saudi Building Code compliance
- An approved plan to keep contractor services and training running during the works
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2025-06-10
Baseline approved at the planning gate
Budget132MFinish2027-01-31
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
50%
3/6 · test result is a pass
Accepted
50%
3/6 · signed off by the business owner
Display options
| REQ-018-01 | Reach the target number of training & test halls | Business | Must | In progress | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | SB-1 | |
| REQ-018-02 | Meet the approved technical specs | Technical | Must | In progress | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | SB-1 | |
| REQ-018-03 | Training and contractor service continue during the works | Functional | Must | In progress | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | SB-1 | |
| REQ-018-04 | Saudi Building Code | Regulatory | Could | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | SB-1 | |
| REQ-018-05 | Civil-defence requirements | Regulatory | Could | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | SB-1 | |
| REQ-018-06 | Site and systems security | Security | Should | In progress | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | SB-1 |
Traceability matrixRequired at this stage
Requirement → deliverable → task → test → acceptance. No requirement has a gap.