Programme · PG-08 · Headquarters & Regional Centres Portfolio

Smart Centres Programme

At risk

Smart test-hall proctoring, the secure enterprise network, the e-test halls and the unified operations centre.

Approved budget
SAR 372M

incl. SAR 10M programme reserve

Actual spend
SAR 138M

⁦37%⁩ of budget

EAC
SAR 370.8M+2.4%

Estimate at completion

Progress
⁦44%⁩

Planned ⁦51%⁩

Schedule performance index
0.90

Cost performance index 0.97

Manager

Eng. Omar H. Bawazir

Director, IT Infrastructure

Sponsor

Eng. Majed S. Al-Rasheed

Head, Digital Transformation Sector

Projects

4 projects

2025-02-16 — 2028-12-31

On track 2At risk 2

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    A unified operations centre that sees the platforms, test halls and buildings in real time

  2. 2

    Cut visitor and trainee entry time at the premises by 45% with smart gates

  3. 3

    Every SCA office and centre on the secure enterprise network

Programme benefits

From baseline to target

  • Premises entry time reduction

    by ⁦2027⁩
    Baseline 0Current 22 %Target 45
  • Offices and centres on the secure network

    by ⁦2027⁩
    Baseline 35Current 64 %Target 100

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
2025202620272028
2026-12-15
2027-03-05
2028-03-31
2028-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Cameras and smart gates connect over the secure enterprise network

  • Critical

    E-test halls need secure enterprise network links

  • The operations centre monitors e-test hall readiness live

  • Proctoring and access are run from the unified operations centre

Shared risks

Risks that hit more than one project, managed at programme level.

12

Excavation permits for fibre to the centres delay the network and everything on it

PRK-08-1·Mitigate·Eng. Omar H. Bawazir

Affects

Open risks in the programme’s projects

5 risks

Open risks in the programme’s projects
  • Critical0
  • High0
  • Medium5
  • Low0
  • Risks 5
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium1 · Medium0 · High0 · Critical
30 · Low0 · Low3 · Medium1 · Medium0 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Eng. Majed S. Al-RasheedManage closelyEng. Omar H. BawazirManage closelyEng. Waleed O. Al-JuhaniManage closelyEng. Yasser M. Al-ZahraniManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

    Committees

    Projects Steering Committee

    Monthly · Quorum ⁦5⁩

    Dr. Mohammed I. Al-Subaie · Head, Strategy & Institutional Excellence SectorEng. Turki A. Al-Anazi · Head, Qualification & Training SectorEng. Majed S. Al-Rasheed · Head, Digital Transformation Sector
    Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-11-03
    Project Approval Committee

    Fortnightly · Quorum ⁦4⁩

    Faisal A. Al-Shehri · Director General, Digital Platforms & Digital Services Portfolio ManagerDr. Amal F. Al-Sudairi · Director General, Strategy & PerformanceTariq S. Al-Yami · Head, Performance & Risk
    Chair: Dr. Noura M. Al-OtaibiNext meeting 2026-11-04

    Programme projects

    The programme’s performance is computed from these projects.

    ⁦4⁩ results
    Export CSV
    Manager
    Smart Test-hall Proctoring & Access ControlPRJ-2026-013Eng. Waleed O. Al-Juhani4ExecutionAt risk⁦79%⁩74M78.7M⁦+6.4%⁩0.88Schedule performance index · 0.880.94Cost performance index · 0.94
    Secure Enterprise NetworkPRJ-2026-018Eng. Omar H. Bawazir4ExecutionAt risk⁦55%⁩132M136.1M⁦+3.1%⁩0.87Schedule performance index · 0.870.97Cost performance index · 0.97
    Electronic Skills-test Halls — Makkah RegionPRJ-2026-022Eng. Yasser M. Al-Zahrani3PlanningOn track⁦2%⁩46M46M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
    Unified Operations Centre for Centres & PlatformsPRJ-2026-024Eng. Omar H. Bawazir1Pre-startOn track⁦0%⁩110M110M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
    Total · 4362M370.8M
    ⁦1⁩–⁦4⁩ of ⁦4⁩

    Budget shares

    Budget shares

    SAR 362M

    Budget

    • Smart Test-hall Proctoring & Access ControlSAR 74M⁦20%⁩
    • Secure Enterprise NetworkSAR 132M⁦36%⁩
    • Electronic Skills-test Halls — Makkah RegionSAR 46M⁦13%⁩
    • Unified Operations Centre for Centres & PlatformsSAR 110M⁦30%⁩
    Budget shares
    CategoryValueShare
    Smart Test-hall Proctoring & Access ControlSAR 74M⁦20%⁩
    Secure Enterprise NetworkSAR 132M⁦36%⁩
    Electronic Skills-test Halls — Makkah RegionSAR 46M⁦13%⁩
    Unified Operations Centre for Centres & PlatformsSAR 110M⁦30%⁩
    TotalSAR 362M⁦100%⁩
    Esc

    Quick actions

    Go to

    Projects

    ↑↓to move↵to openEscto close