RSK-0035Qassim Vocational Qualification Centre
Pile lengths exceeding contract quantities
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Gaps between contract and site quantities
Preventive controls
- Re-measure quantities with the supervising consultant
- Value engineering on the costliest items
2 / 2
Event
Pile lengths exceeding contract quantities
Quantity variance above 5% of contract value
Contingency
Defer non-critical items to a later phase
Impact
Extra variations and contingency drawn down
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 8.4M
Residual
75% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 5 days ago · Outside the engine — below «high»
Project manager
Current levelEng. Ahmed Y. Asiri
Currently followed up here- 2
Programme manager
Eng. Ahmed Y. Asiri
- 3
PMO director
Dr. Noura M. Al-Otaibi
- 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Re-measure quantities with the supervising consultant
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saIn progressIn 48 days2026-12-156 Rajab 1448 AHValue engineering on the costliest items
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saNot startedIn 48 days2026-12-156 Rajab 1448 AH
Trigger
Quantity variance above 5% of contract value
Contingency
Defer non-critical items to a later phase