Saudi Contractors AuthorityMunjaz11My actionsNotifications

RSK-0034Qassim Vocational Qualification Centre

Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16

20CriticalEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Clay layers and voids under the southern part of the site that the initial soil tests missed

Preventive controls

  • Extra soil tests at axes 12 to 16
  • A change request to redesign the foundations
  • Dewatering at axis 14

1 / 3

Event

Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16

20CriticalTrigger

Excavation stopped at any axis for more than 10 days

Contingency

Switch to deeper rotary-bored piles

Impact

Foundations of five axes redesigned, 55 days late, SAR 27M

SAR 27M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
20Critical

Residual

5
4
3
2
1
1
2
3
4
5
8Medium

Exposure

SAR 27M

Residual

⁦60⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 5 days ago

  1. Project manager

    Eng. Ahmed Y. Asiri

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Ahmed Y. Asiri

    Automatically at 15 days unreviewed · in 10 days
  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 15 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦2⁩ of ⁦3⁩ done
  • Extra soil tests at axes 12 to 16

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa
    Done⁦2026-10-20⁩2026-10-209 Jumada I 1448 AH
  • A change request to redesign the foundations

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa
    Done⁦2026-09-28⁩2026-09-2817 Rabiʻ II 1448 AH
  • Dewatering at axis 14

    Eng. Adel S. Al-AmoudiEng. Adel S. Al-AmoudiSenior Site Engineer (Contractor)P-043a.alamoudi@sca.sa
    In progressIn 11 days2026-11-0828 Jumada I 1448 AH

Trigger

Excavation stopped at any axis for more than 10 days

Contingency

Switch to deeper rotary-bored piles

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close