Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-022On track3PlanningStage-Gate

Electronic Skills-test Halls — Makkah Region

Add to watchlist

Fit out 180 secure e-test seats with recording and proctoring in Jeddah, Makkah and Taif, co-funded with a partner entity.

Budget (BAC)

SAR 46M

Actual cost

SAR 920K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 46M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+9

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦2%⁩ done against ⁦2%⁩ planned.

SPI ⁦1.00⁩, CPI ⁦1.00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Specialised, Value-adding ServicesSO-3.3A better contractor experience and service quality

Main initiative

SI-3.3.1Smart centres

Contribution to the initiative⁦13%⁩

The project’s share of the initiative’s project budget (4 projects)

Secondary links

Annual work-plan line
WP-2026-022
Classification
External

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦2%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦98%⁩

1 deliverable accepted

  • Project plan & baseline⁦2%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦1⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦2%⁩ of budget

    920K/ 46M
    Actual spend
    920K
    Committed
    1.1M
    Approved budget
    46M
    Estimate at completion
    46M

    Next milestones

    • Contract signed⁦2026-11-07⁩On track
    • 50% of works complete⁦2027-06-08⁩On track
    • Provisional acceptance⁦2028-02-11⁩On track
    • Closure⁦2028-03-31⁩On track

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • No actions on this project

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    1 open risk, exposure SAR 900K

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0047Privacy requirements for e-test recordings under the Personal Data Protection LawProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical0
    • High0
    • Medium1
    • Low0

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦1⁩ of ⁦12⁩ approved

    • Project plan & baseline022-D1 · V1 · CRT-022-01⁦2%⁩Eng. Yasser M. Al-Zahrani⁦2026-10-18⁩2026-10-187 Jumada I 1448 AHApproved
    • Monitoring & reporting022-D2 · V0⁦3%⁩Eng. Bandar M. Al-ShammariIn 38 days2026-12-0525 Jumada II 1448 AHDraft
    • Detailed design022-D3 · V0⁦6%⁩Eng. Bandar M. Al-ShammariIn 86 days2027-01-2214 Shaʻban 1448 AHDraft
    • Permits & approvals022-D4 · V0⁦6%⁩Eng. Majed S. Al-RasheedIn 135 days2027-03-124 Shawwal 1448 AHDraft
    • Site works & excavation022-D5 · V0⁦13%⁩Eng. Majed S. Al-RasheedIn 183 days2027-04-2922 Dhuʻl-Qiʻdah 1448 AHDraft
    • Structure022-D6 · V0⁦13%⁩Eng. Yasser M. Al-ZahraniIn 231 days2027-06-1611 Muharram 1449 AHDraft
    • Finishes022-D7 · V0⁦13%⁩Eng. Bandar M. Al-ShammariIn 279 days2027-08-031 Rabiʻ I 1449 AHDraft
    • Supply022-D8 · V0⁦10%⁩Eng. Yasser M. Al-ZahraniIn 327 days2027-09-2019 Rabiʻ II 1449 AHDraft
    • Installation022-D9 · V0⁦10%⁩Eng. Bandar M. Al-ShammariIn 375 days2027-11-078 Jumada II 1449 AHDraft
    • Testing & commissioning022-D10 · V0⁦10%⁩Eng. Majed S. Al-RasheedIn 424 days2027-12-2628 Rajab 1449 AHDraft
    • Provisional acceptance022-D11 · V0⁦7%⁩Eng. Bandar M. Al-ShammariIn 472 days2028-02-1216 Ramadan 1449 AHDraft
    • Final acceptance022-D12 · V0⁦7%⁩Eng. Majed S. Al-RasheedIn 520 days2028-03-315 Dhuʻl-Qiʻdah 1449 AHDraft

    Team, contracts & documents

    Team

    2 members

    Eng. Yasser M. Al-Zahrani · Director, CybersecurityEng. Sultan F. Al-Ghamdi · Project Manager, Muqawil Platform — Release 4
    • Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityProject managerP-026y.alzahrani@sca.sa⁦30%⁩
    • Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Muqawil Platform — Release 4Integration adviser, e-test halls with MuqawilP-005s.alghamdi@sca.sa⁦15%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house

    Documents

    • No documents yet

    Meetings

    • No meetings scheduled
    Esc

    Quick actions

    Go to

    Projects

    ↑↓to move↵to openEscto close