Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-022On track3PlanningStage-Gate

Electronic Skills-test Halls — Makkah Region

Add to watchlist

Fit out 180 secure e-test seats with recording and proctoring in Jeddah, Makkah and Taif, co-funded with a partner entity.

Budget (BAC)

SAR 46M

Actual cost

SAR 920K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 46M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work44.6M⁦17⁩ elements
Unallocated contingency1.4MSAR 2.3M
Budget at completion46MPRJ-2026-022
Weighted progress⁦2%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project609⁦2026-08-02⁩⁦2028-04-02⁩⁦2%⁩44.620.92—
1
Phase159⁦2026-08-02⁩⁦2027-01-08⁩⁦34%⁩2.680.92—
1.1
WBS element112⁦2026-08-02⁩⁦2026-11-22⁩⁦67%⁩1.340.920 / 1
1.2
WBS element72⁦2026-10-28⁩⁦2027-01-08⁩⁦0%⁩1.34—1 / 2
2
Phase117⁦2026-12-12⁩⁦2027-04-08⁩⁦0%⁩5.35——
2.1
WBS element72⁦2026-12-12⁩⁦2027-02-22⁩⁦0%⁩2.68—1 / 1
2.2
WBS element72⁦2027-01-26⁩⁦2027-04-08⁩⁦0%⁩2.68—1 / 2
3
Phase162⁦2027-03-12⁩⁦2027-08-21⁩⁦0%⁩16.96——
3.1
WBS element72⁦2027-03-12⁩⁦2027-05-23⁩⁦0%⁩5.65—1 / 1
3.2
WBS element72⁦2027-04-26⁩⁦2027-07-07⁩⁦0%⁩5.65—1 / 1
3.3
WBS element72⁦2027-06-10⁩⁦2027-08-21⁩⁦0%⁩5.65—1 / 2
4
Phase162⁦2027-07-25⁩⁦2028-01-03⁩⁦0%⁩13.39——
4.1
WBS element72⁦2027-07-25⁩⁦2027-10-05⁩⁦0%⁩4.46—1 / 1
4.2
WBS element72⁦2027-09-08⁩⁦2027-11-19⁩⁦0%⁩4.46—1 / 1
4.3
WBS element72⁦2027-10-23⁩⁦2028-01-03⁩⁦0%⁩4.46—1 / 2
5
Phase117⁦2027-12-07⁩⁦2028-04-02⁩⁦0%⁩6.25——
5.1
WBS element72⁦2027-12-07⁩⁦2028-02-17⁩⁦0%⁩3.12—1 / 1
5.2
WBS element72⁦2028-01-21⁩⁦2028-04-02⁩⁦0%⁩3.12—1 / 1
Total⁦2%⁩44.620.92
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close