Saudi Contractors Authority
Project charter
Electronic Skills-test Halls — Makkah Region
APPROVEDV2Approved 2026-07-31
1Project identity
Required at this stage- Project name
- Electronic Skills-test Halls — Makkah Region
- Project code
- PRJ-2026-022
- Project sponsor
- Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa
- Project manager
- Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa
- Project owner
- Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa
- Portfolio & programme
- Headquarters & Regional Centres PortfolioSmart Centres Programme
- Type & methodology
- Infrastructure · Stage-Gate
- Current phase
- 3Planning
2Background & rationale
Required at this stageFit out 180 secure e-test seats with recording and proctoring in Jeddah, Makkah and Taif, co-funded with a partner entity.
3Objectives
Required at this stage- 1A better contractor experience and service quality
- 2SCA services and programmes in every region
Serves the strategic objectives:SO-3.3A better contractor experience and service qualitySO-3.1SCA services and programmes in every region
4Scope
Required at this stageIn scope
- Fit out 180 secure e-test seats with recording and proctoring in Jeddah, Makkah and Taif, co-funded with a partner entity.
- Saudi Building Code compliance
- An approved plan to keep contractor services and training running during the works
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
5High-level requirements
Required at this stage- 1Saudi Building Code compliance
- 2An approved plan to keep contractor services and training running during the works
- 3Civil-defence requirements
6Deliverables
Required at this stage| 1 | Project management plan | 2026-08-26 |
| 2 | Main deliverable — stage 1 | 2027-06-08 |
| 3 | Main deliverable — final stage | 2028-01-06 |
| 4 | Final report | 2028-03-31 |
7Key milestones
Required at this stage- Charter approved2026-07-31
- Contract signed2026-11-07
- 50% of works complete2027-06-08
- Provisional acceptance2028-02-11
- Closure2028-03-31
8Budget
Required at this stage- Main contract72.0%33.1M
- Supervision & consulting14.1%6.5M
- Internal team8.9%4.1M
- Contingency reserve (5%)5.0%2.3M
The owning sector’s approved budgetTotal46M
9Timeline
Required at this stage10Key risks
Required at this stage- MediumPrivacy requirements for e-test recordings under the Personal Data Protection Law
11Constraints
Required at this stage- Stay within the approved budget
- Comply with the Government Tenders & Procurement Law
12Assumptions
Required at this stage- Named internal staff available throughout
- Approvals land within the workflow’s action time limits
13Stakeholders
Required at this stage- Project sponsorDecisions and funding
- Project ownerAccepts deliverables, owns benefits
- Project Management Office (PMO)Governance and compliance
14Success criteria
Required at this stage- 1Delivered within the approved budget
- 2On the approved date ±5%
- 3Target benefits within 12 months
15Governance structure
Required at this stage- Change Control BoardApproves scope, cost and schedule changesWeekly
- PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
- Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly