Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-024On track1Pre-startStage-Gate

Unified Operations Centre for Centres & Platforms

Add to watchlist

A 24/7 operations centre watching the digital platforms, the test halls and the Authority’s buildings in every region.

Budget (BAC)

SAR 110M

Actual cost

SAR 0

⁦0%⁩ of budget

Progress

⁦0%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 110M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

Pre-startStage ⁦1⁩ of ⁦5⁩

Next gate:Initiation4 November 2026

  1. Pre-start · Current stagePre-start · Current stage
  2. Gate into «Initiation»DecisionNot held yetDate4 November 2026Initiation · Not startedInitiation · Not started
  3. Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+4

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦0%⁩ done against ⁦0%⁩ planned.

SPI ⁦1.00⁩, CPI ⁦1.00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Specialised, Value-adding ServicesSO-3.3A better contractor experience and service quality

Main initiative

SI-3.3.1Smart centres

Contribution to the initiative⁦30%⁩

The project’s share of the initiative’s project budget (4 projects)

Secondary links

Annual work-plan line
WP-2027-024
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦0%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦100%⁩

0 deliverables accepted

    0 deliverables under inspection or acceptance

      Progress & earned value

      ⁦0⁩ of ⁦5⁩ milestones complete

      Earned-value curve

      Planned, earned and actual to the data date, cumulative, with the forecast cost tail

      • Planned value
      • Earned value
      • Actual cost
      • Estimate at completion
      • Budget at completion

      Budget & commitments

      Commitments are ⁦0%⁩ of budget

      0/ 110M
      Actual spend
      0
      Committed
      0
      Approved budget
      110M
      Estimate at completion
      110M

      Next milestones

      • Charter approved⁦2027-01-01⁩On track
      • Contract signed⁦2027-04-29⁩On track
      • 50% of works complete⁦2028-01-09⁩On track
      • Provisional acceptance⁦2028-11-03⁩On track
      • Closure⁦2028-12-31⁩On track

      Waiting on someone

      ⁦0⁩ approvals and ⁦0⁩ open actions on this project

      Approvals & requests

      From «My actions» for this project

      • No approvals pending

      Actions

      ⁦0⁩ open

      • No actions on this project

      Change requests

      Cost and schedule impact

      • No change requests

      Risks & impediments

      0 open risks, exposure SAR 0

      Risk map

      Probability
      5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
      4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
      3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
      2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
      1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
      12345

      Impact

      • Critical0
      • High0
      • Medium0
      • Low0

      Top risks

      • No open risks

      Open impediments

      ⁦0⁩ escalated

      • No open impediments

      Deliverables

      ⁦0⁩ of ⁦12⁩ approved

      • Project plan & baseline024-D1 · V0⁦3%⁩Eng. Omar H. BawazirIn 159 days2027-04-0528 Shawwal 1448 AHDraft
      • Monitoring & reporting024-D2 · V0⁦3%⁩Eng. Turki A. Al-AnaziIn 217 days2027-06-0227 Dhuʻl-Hijjah 1448 AHDraft
      • Detailed design024-D3 · V0⁦6%⁩Eng. Turki A. Al-AnaziIn 275 days2027-07-3026 Safar 1449 AHDraft
      • Permits & approvals024-D4 · V0⁦6%⁩Eng. Majed S. Al-RasheedIn 333 days2027-09-2625 Rabiʻ II 1449 AHDraft
      • Site works & excavation024-D5 · V0⁦13%⁩Eng. Majed S. Al-RasheedIn 391 days2027-11-2324 Jumada II 1449 AHDraft
      • Structure024-D6 · V0⁦13%⁩Eng. Omar H. BawazirIn 448 days2028-01-1922 Shaʻban 1449 AHDraft
      • Finishes024-D7 · V0⁦12%⁩Eng. Turki A. Al-AnaziIn 506 days2028-03-1721 Shawwal 1449 AHDraft
      • Supply024-D8 · V0⁦10%⁩Eng. Omar H. BawazirIn 564 days2028-05-1419 Dhuʻl-Hijjah 1449 AHDraft
      • Installation024-D9 · V0⁦10%⁩Eng. Turki A. Al-AnaziIn 622 days2028-07-1118 Safar 1450 AHDraft
      • Testing & commissioning024-D10 · V0⁦10%⁩Eng. Majed S. Al-RasheedIn 679 days2028-09-0616 Rabiʻ II 1450 AHDraft
      • Provisional acceptance024-D11 · V0⁦7%⁩Eng. Turki A. Al-AnaziIn 737 days2028-11-0316 Jumada II 1450 AHDraft
      • Final acceptance024-D12 · V0⁦7%⁩Eng. Majed S. Al-RasheedIn 795 days2028-12-3115 Shaʻban 1450 AHDraft

      Team, contracts & documents

      Team

      1 member

      Eng. Omar H. Bawazir · Director, IT Infrastructure
      • Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureProject manager — unified operations centre studyP-024o.bawazir@sca.sa⁦25%⁩

      Contracts

      0 contracts

      • No external contracts — delivered in-house

      Documents

      • No documents yet

      Meetings

      • No meetings scheduled
      Esc

      Quick actions

      Go to

      Projects

      ↑↓to move↵to openEscto close