RSK-0036Arar Vocational Qualification Centre

Municipality late bringing utilities and access roads to the site

16HighOpenMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Price swings and unplanned financial commitments

Preventive controls

  • Monthly EAC monitoring
  • Fix prices in the coming purchase orders

2 / 2

Event

Municipality late bringing utilities and access roads to the site

16HighTrigger

EAC above budget by more than 5%

Contingency

Reallocate from the portfolio reserve

Impact

Budget overrun and the need for more funding

SAR 14M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SAR 14M

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 56 days ago

  1. Project manager

    Eng. Ibrahim A. Al-Ghamdi

    Currently followed up here
  2. Programme manager

    Eng. Ahmed Y. Asiri

    Automatically at 15 days unreviewed · threshold passed 41 days ago
  3. PMO director

    Current level

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · threshold passed 36 days ago
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Monthly EAC monitoring

    Yousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & EventsP-016y.alomari@sca.sa
    In progressIn 64 days2026-12-3122 Rajab 1448 AH
  • Fix prices in the coming purchase orders

    Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa
    Not startedIn 64 days2026-12-3122 Rajab 1448 AH

Trigger

EAC above budget by more than 5%

Contingency

Reallocate from the portfolio reserve

Esc