PRJ-2026-013At risk4ExecutionConstruction
Smart Test-hall Proctoring & Access Control
Add to watchlist4,200 cameras and smart entry gates across HQ, branches and qualification centres, with a central monitoring room and automatic identity checks for test takers, starting at the Qassim centre.
Project managerEng. Waleed O. Al-JuhaniProject sponsorEng. Turki A. Al-AnaziProgrammeSmart Centres Programme
Early warning: 58% chance of slipping within 45 days
Budget (BAC)
SAR 74M
Actual cost
SAR 62.2M
84% of budget
Progress
79%Awaiting acceptance 9%
Estimate at completion
SAR 78.7M
SAR +4.7M
SPI · CPI
0.88Schedule performance index · 0.880.94Cost performance index · 0.94
Forecast finish
2026-12-15
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started