Original
Original baseline
- Finish
- 2026-10-31
- Budget
- SAR 74M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-02-16 · by Eng. Turki A. Al-Anazi
4,200 cameras and smart entry gates across HQ, branches and qualification centres, with a central monitoring room and automatic identity checks for test takers, starting at the Qassim centre.
Budget (BAC)
Actual cost
84% of budget
Progress
Estimate at completion
SAR +4.7M
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-02-16 · by Eng. Turki A. Al-Anazi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Waleed O. Al-Juhani
What changed from version A to version B
Finish
2026-10-312027-01-11
+72 days
Budget
SAR 74MSAR 74M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference