PRJ-2026-013At risk4ExecutionConstruction
Smart Test-hall Proctoring & Access Control
Add to watchlist4,200 cameras and smart entry gates across HQ, branches and qualification centres, with a central monitoring room and automatic identity checks for test takers, starting at the Qassim centre.
Project managerEng. Waleed O. Al-JuhaniProject sponsorEng. Turki A. Al-AnaziProgrammeSmart Centres Programme
Early warning: 58% chance of slipping within 45 days
Budget (BAC)
SAR 74M
Actual cost
SAR 62.2M
84% of budget
Progress
79%Awaiting acceptance 9%
Estimate at completion
SAR 78.7M
SAR +4.7M
SPI · CPI
0.88Schedule performance index · 0.880.94Cost performance index · 0.94
Forecast finish
2026-12-15
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-013-2026-10 | Draft | 79% | — | 2026-10-26 |
| September 2026UPD-013-2026-09 | Approved | 75% | — | 2026-10-02 |
| August 2026UPD-013-2026-08 | Approved | 70% | — | 2026-09-02 |