CP-2026-04Version 1
Qassim Vocational Qualification Centre
One corrective plan: why the project slipped, the rule that triggered it, the actions, the days won back, approval and follow-up.
What triggered the plan
The project’s reading the day the rule fired, and today.
Detected on 2026-08-04
Slip past the baseline
- At detection
- 55 days
- Today
- 64 days
- Limit
- > 40
Schedule performance index
- At detection
- 0.83
- Today
- 0.80
- Limit
- < 0.85
A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.
Days won back
The forecast finish without the plan, with it, and the difference.
Baseline
2027-05-31Without the plan
2027-09-05+97 days
With the plan
2027-08-03+64 days
Wins back 33 days
Achieved so far: 0 days
Why it slipped
Clay layers, voids and groundwater under the foundations of axes 12 to 16 that the initial soil tests missed
Corrective actions
Each action with its owner, date, status and the days it wins back; overdue ones are shaded.
Extra soil tests at axes 12 to 16
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saDone2026-10-202026-10-209 Jumada I 1448 AHRedesign the foundations through a change request
In progressIn 7 days2026-11-0424 Jumada I 1448 AHWins back 10 daysDewatering at axis 14
Eng. Adel S. Al-AmoudiEng. Adel S. Al-AmoudiSenior Site Engineer (Contractor)P-043a.alamoudi@sca.saIn progressIn 11 days2026-11-0828 Jumada I 1448 AHWins back 8 daysApprove the geotechnical report for axes 12–16
In progressIn 11 days2026-11-0828 Jumada I 1448 AHA second shift on the concrete frame once the foundations are done
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saNot startedIn 34 days2026-12-0121 Jumada II 1448 AHWins back 15 days
Follow-up
The project’s readings after the plan was approved, with the PMO’s notes.
2026-10-27Karim Haddad64 days lateSPI 0.80
Groundwater stopped excavation at axis 14 (ISS-0123); no days won back yet
2026-09-29Karim Haddad60 days lateSPI 0.81
Extra soil tests complete; the redesign request is filed