Saudi Contractors AuthorityMunjaz11My actionsNotifications

CP-2026-04Version ⁦1⁩

Qassim Vocational Qualification Centre

Approved — under wayOff track

One corrective plan: why the project slipped, the rule that triggered it, the actions, the days won back, approval and follow-up.

What triggered the plan

The project’s reading the day the rule fired, and today.

Detected on ⁦2026-08-04⁩

Slip past the baseline

At detection
55 days
Today
64 days
Limit
> 40

Schedule performance index

At detection
0.83
Today
0.80
Limit
< 0.85

A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.

Days won back

The forecast finish without the plan, with it, and the difference.

  1. Baseline

    2027-05-31
  2. Without the plan

    2027-09-05

    +97 days

  3. With the plan

    2027-08-03

    +64 days

Wins back 33 days

Achieved so far: 0 days

Why it slipped

Clay layers, voids and groundwater under the foundations of axes 12 to 16 that the initial soil tests missed

Corrective actions

Each action with its owner, date, status and the days it wins back; overdue ones are shaded.

⁦1⁩ of ⁦5⁩ done
  • Extra soil tests at axes 12 to 16

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa
    Done⁦2026-10-20⁩2026-10-209 Jumada I 1448 AH
  • Redesign the foundations through a change request

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saCR-2026-010
    In progressIn 7 days2026-11-0424 Jumada I 1448 AHWins back 10 days
  • Dewatering at axis 14

    Eng. Adel S. Al-AmoudiEng. Adel S. Al-AmoudiSenior Site Engineer (Contractor)P-043a.alamoudi@sca.sa
    In progressIn 11 days2026-11-0828 Jumada I 1448 AHWins back 8 days
  • Approve the geotechnical report for axes 12–16

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saACT-0320
    In progressIn 11 days2026-11-0828 Jumada I 1448 AH
  • A second shift on the concrete frame once the foundations are done

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa
    Not startedIn 34 days2026-12-0121 Jumada II 1448 AHWins back 15 days

Follow-up

The project’s readings after the plan was approved, with the PMO’s notes.

  1. 2026-10-27Karim Haddad64 days lateSPI ⁦0.80⁩

    Groundwater stopped excavation at axis 14 (ISS-0123); no days won back yet

  2. 2026-09-29Karim Haddad60 days lateSPI ⁦0.81⁩

    Extra soil tests complete; the redesign request is filed

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close