Execution
Corrective plan
Actions, owners, dates and status
- Form no.
- SCA-PMO-F11
- Template edition
- 1.4
- Version
- V1
- Form date
- 2026-08-18
- Hijri
- 5 Rabiʻ I 1448 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-020
- Project
- Qassim Vocational Qualification Centre
- Portfolio
- Headquarters & Regional Centres Portfolio
- Sector
- Corporate Support Sector
- Sponsor
- Eng. Turki A. Al-Anazi
- Project manager
- Eng. Ahmed Y. Asiri
1Why the planAuto-filled
Slip when detected
55 days
SPI
0.83
Finish without the plan
2027-09-05
Finish with the plan
2027-08-03
Causes
Clay layers, voids and groundwater under the foundations of axes 12 to 16 that the initial soil tests missed
2Actions
| Action | Owner | Due | Status | Days won back |
|---|---|---|---|---|
| Extra soil tests at axes 12 to 16 | Eng. Ahmed Y. Asiri | 2026-10-20 | Done | 0 |
| Redesign the foundations through a change request | Eng. Ahmed Y. Asiri | 2026-11-04 | In progress | 10 |
| Dewatering at axis 14 | Eng. Adel S. Al-Amoudi | 2026-11-08 | In progress | 8 |
| Approve the geotechnical report for axes 12–16 | Eng. Ahmed Y. Asiri | 2026-11-08 | In progress | 0 |
| A second shift on the concrete frame once the foundations are done | Eng. Ahmed Y. Asiri | 2026-12-01 | Not started | 15 |
| Total | — | — | — | 33 |
3PMO follow-upAuto-filled
| Date | SPI | Slip | Note |
|---|---|---|---|
| 2026-10-27 | 0.80 | 64 | Groundwater stopped excavation at axis 14 (ISS-0123); no days won back yet |
| 2026-09-29 | 0.81 | 60 | Extra soil tests complete; the redesign request is filed |
Approval logChain: Corrective plan approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Ahmed Y. AsiriDirector, Construction Projects | Submitted | — | 2026-08-18 13:10 |
| 2 | Programme manager review | Technical acceptance | Dr. Noura M. Al-OtaibiProgramme manager | Approved | — | 2026-08-19 09:42 |
| 3 | Projects Steering Committee approval | Technical acceptance | Dr. Abdullah S. Al-QahtaniProjects Steering Committee | Approved | — | 2026-08-25 11:56 |
Signatures
Programme manager review
Dr. Noura M. Al-Otaibi
Approved2026-08-19
Projects Steering Committee approval
Dr. Abdullah S. Al-Qahtani
Approved2026-08-25