Original
Original baseline
- Finish
- 2027-05-31
- Budget
- SAR 345M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2024-06-02 · by Eng. Turki A. Al-Anazi
A training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.
Budget (BAC)
Actual cost
46% of budget
Progress
Estimate at completion
SAR +18.2M
SPI · CPI
Forecast finish
64 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure5 March 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2024-06-02 · by Eng. Turki A. Al-Anazi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Ahmed Y. Asiri
What changed from version A to version B
Finish
2027-05-312027-08-01
+62 days
Budget
SAR 345MSAR 353.4M
+8.40 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference