Qassim Vocational Qualification Centre
Remove from watchlistA training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.
Budget (BAC)
Actual cost
46% of budget
Progress
Estimate at completion
SAR +18.2M
SPI · CPI
Forecast finish
64 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure5 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Initiation»DecisionGoDate3 April 2024All criteria and required documents met.Pre-startComplete
- Gate into «Planning»DecisionGoDate2 June 2024All criteria and required documents met.InitiationComplete
- Gate into «Execution»DecisionGoDate24 November 2024All criteria and required documents met.PlanningComplete
- Gate into «Closure»DecisionNot held yetDate5 March 2027ExecutionCurrent stageCurrent stage
- 5ClosureNot started
What each stage requires
The documents and approvals each gate asks for before the next stage.
Closure gate — deliverables accepted and handed over
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 2 mandatory checklist items open
- 3 required documents not approved
- Weighted score 74 under the pass mark 75
Checklist
5 of 7 done
- Deliverable completion certificates approved for every deliverableMandatory
- Acceptance tests and handover to operations completeMandatory
- Open commitments listed with a plan to close themMandatory
- Deliverable-linked payments settledMandatory
- Pilot run with no critical or high findingsMandatory
- Users trained
- Launch rollback plan
Required documents
1 of 4 approved
- Deliverable completion certificatesApproved · V1
- Project closure & handover formSubmitted — awaiting acceptance · V1
- Lessons-learned logNot submitted
- Benefits measurement planNot submitted
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables acceptedweight 35%Met
Awaiting evidence from the project team.
Quality & securityweight 25%Met
Awaiting evidence from the project team.
Operations & handover readinessweight 25%Met
Awaiting evidence from the project team.
User & training readinessweight 15%
Awaiting evidence from the project team.
Approvers
Project Management Office
- Dr. Noura M. Al-OtaibiPMO directorVote pending
- Eng. Bandar M. Al-ShammariProject ownerVote pending
- Eng. Turki A. Al-AnaziProject sponsorVote pending