PRJ-2026-020Off track4ExecutionConstruction

Qassim Vocational Qualification Centre

Remove from watchlist

A training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 345M

Actual cost

SAR 159.8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 363.2M

SAR +18.2M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 345M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 18.2M
EAC SAR 363.2M
Revised request SAR 353.4M
  • Actual spendSAR 159.8M
  • Committed, not spentSAR 156.2M
  • Allotted, uncommittedSAR 18.7M
  • Contingency availableSAR 10.4M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 327.8M
Original budgetwhen the first baseline was approved
SAR 345M
Approved budgetafter approved change requests
SAR 345M
Current budgetavailable to spend now
SAR 345M
Revised budgetif the pending changes are approved
SAR 353.4M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 316M
Contracts2 active contracts
SAR 307.4M
Purchase orders⁦3⁩ orders
SAR 8.6M
Remaining budgetapproved less actual
SAR 185.2M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 159.8M
Accrualswork done, not yet invoiced
SAR 6.4M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 363.2M
ContingencySAR 6.9M drawn of SAR 17.3M
SAR 10.4M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 327.8M
ApprovedSAR 345M
Estimate at completionSAR 363.2M
Approved is SAR 17.2M (⁦5.2%⁩) above the estimate
The estimate at completion is SAR 35.4M (⁦10.8%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-03-19⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-71020
  • WBS elements⁦5⁩ elements · P-2026-020.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦36⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 6.9M drawn of SAR 17.3M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 6.9M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance20.0821.8121.8121.81⁦−1.73⁩
2Design & permits40.1643.6143.6143.61⁦−3.45⁩
3Civil works127.17122.8394.37130.47⁦−3.31⁩
4MEP works100.4087.110.00110.52⁦−10.12⁩
5Handover46.8540.650.0051.58⁦−4.72⁩
Unallocated contingency10.350.000.005.18⁦+5.18⁩
Total345.00316.00159.79363.16⁦−18.16⁩

Budget split

WBS

SAR 345M

Budget

  • Management & governanceSAR 20.1M⁦6%⁩
  • Design & permitsSAR 40.2M⁦12%⁩
  • Civil worksSAR 127.2M⁦37%⁩
  • MEP worksSAR 100.4M⁦29%⁩
  • HandoverSAR 46.9M⁦14%⁩
  • Unallocated contingencySAR 10.4M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2029-08-30⁩+822

SPI(t) ⁦0.57⁩ against the approved finish ⁦2027-05-31⁩

Planned valuePV
SAR 310.9M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 151.8M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 159.8M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 345M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−7.99⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−159.14⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.95
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.49
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 363.2M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 203.4M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−18.16⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.04
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 363.2M
  • If the rest goes to planSAR 353M
  • At cost and schedule performanceSAR 576.4M
  • The PM’s bottom-up estimateSAR 363.2M
  • To stay within SAR 345M, cost performance on the rest must rise to ⁦1.04⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 363.2M

Variance at completion: ⁦−18.16⁩ SAR M