PRJ-2026-004 · From item 2
Al-Khobar Branch — Rehabilitation & ExtensionPlanned to date 92%
- SPI
- 0.74
- Forecast finish
- 2027-02-03
- Budget
- SAR 412M
126 days lateMaterial risks: 2Open impediments: 3Corrective plan CP-2026-02
Rulings on the Al-Khobar branch and the Academy campus; the Muqawil corrective plan and a first reading of the 2027 projects budget.
Starts in
10 min2026-10-2817 Jumada I 1448 AH · 10:00
80 of 90 min
Approve the previous minutes
ApprovalDr. Noura M. Al-Otaibi
5 min
Direct payment to subcontractors at the Al-Khobar branch
DecisionEng. Turki A. Al-Anazi
20 min
Academy campus claims: dispute board or settlement
DecisionEng. Abdulrahman S. Al-Harbi
20 min
Muqawil — updated corrective plan
DiscussionEng. Majed S. Al-Rasheed
15 min
First reading of the 2027 projects budget
For informationMunirah A. Al-Khalidi
15 min
Any other business
DiscussionDr. Abdullah S. Al-Qahtani
5 min
What will be presented and what needs a decision — read before the meeting
Approve the previous minutes
ApprovalPresented by Dr. Noura M. Al-Otaibi5 min
Direct payment to subcontractors at the Al-Khobar branch
DecisionPresented by Eng. Turki A. Al-Anazi20 minPRJ-2026-004
Needs a committee decision
Academy campus claims: dispute board or settlement
DecisionPresented by Eng. Abdulrahman S. Al-Harbi20 minPRJ-2026-007
Needs a committee decision
Muqawil — updated corrective plan
DiscussionPresented by Eng. Majed S. Al-Rasheed15 minPRJ-2026-014
First reading of the 2027 projects budget
For informationPresented by Munirah A. Al-Khalidi15 min2027 annual work plan
Any other business
DiscussionPresented by Dr. Abdullah S. Al-Qahtani5 min
From this committee’s earlier meetings and decisions — reviewed at the start
ACT-0307 · Khalid N. Al-Mutairi
ACT-0321 · Haifa S. Al-Ruwaili
Quorum: Four of five members, including the chair or a named deputy
At least 4 voting members needed
3 files
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
The summary is available once the meeting has been held and minuted.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-004 · From item 2
Al-Khobar Branch — Rehabilitation & ExtensionPlanned to date 92%
126 days lateMaterial risks: 2Open impediments: 3Corrective plan CP-2026-02
PRJ-2026-007 · From item 3
SCA Academy Campus, RiyadhPlanned to date 82%
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
PRJ-2026-014 · From item 4
Muqawil Platform — Release 4Planned to date 67%
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Agenda item needing a decision · PRJ-2026-004
Direct payment to subcontractors at the Al-Khobar branchFrom item 2
Agenda item needing a decision · PRJ-2026-007
Academy campus claims: dispute board or settlementFrom item 3
Change request awaiting decision · CR-2026-004
Add membership transfer & record merge to the first releaseMuqawil Platform — Release 4
Change request awaiting decision · CR-2026-005
Variation 7: revise the central HVAC systemSCA Academy Campus, Riyadh
Change request awaiting decision · CR-2026-006
Extend the contract by 150 daysSCA Academy Campus, Riyadh
Corrective plan awaiting approval · CP-2026-01
Muqawil Platform — Release 4Corrective plan awaiting approval · CP-2026-03
SCA Academy Campus, RiyadhISS-0113 · Al-Khobar Branch — Rehabilitation & Extension
FundingSAR 6.4M· Asked from: Executive Committee
Approve paying four subcontractors directly from certificate 34, deducted from the main contractor
ISS-0109 · SCA Academy Campus, Riyadh
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade alternative on the consultant’s advice, or to extend the supply period
ISS-0103 · Muqawil Platform — Release 4
PeopleSAR 980K· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ISS-0101 · Muqawil Platform — Release 4
Coordination· Asked from: Dr. Abdullah S. Al-Qahtani
A letter from the Secretary-General to the National Information Center for a dedicated test environment for three months
CP-2026-01 · Muqawil Platform — Release 4
PeopleSAR 980K· Asked from: Change Committee
Approve change request CR-2026-012 for three integration engineers
CP-2026-03 · SCA Academy Campus, Riyadh
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade on the consultant’s advice
ACT-0307 · Khalid N. Al-Mutairi
ACT-0311 · Eng. Ibrahim A. Al-Ghamdi