PRJ-2026-014 · From item 2
Muqawil Platform — Release 4Planned to date 67%
- SPI
- 0.87
- Forecast finish
- 2027-05-12
- Budget
- SAR 86.4M
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Change requests, week 44.
Scheduled for
13:002026-10-2918 Jumada I 1448 AH · 13:00
55 of 60 min
Approve the previous minutes
ApprovalEng. Ibrahim A. Al-Ghamdi
5 min
Add membership transfer & record merge
DecisionEng. Reem K. Al-Dosari
20 min
Add vendor integration capacity
DecisionEng. Sultan F. Al-Ghamdi
15 min
Re-route the enterprise network in Al-Rawdah
DecisionEng. Omar H. Bawazir
15 min
What will be presented and what needs a decision — read before the meeting
Approve the previous minutes
ApprovalPresented by Eng. Ibrahim A. Al-Ghamdi5 min
Add membership transfer & record merge
DecisionPresented by Eng. Reem K. Al-Dosari20 minCR-2026-004
Needs a committee decision
Add vendor integration capacity
DecisionPresented by Eng. Sultan F. Al-Ghamdi15 minCR-2026-012
Needs a committee decision
Re-route the enterprise network in Al-Rawdah
DecisionPresented by Eng. Omar H. Bawazir15 minCR-2026-014
Needs a committee decision
From this committee’s earlier meetings and decisions — reviewed at the start
ACT-0312 · Eng. Abdulrahman S. Al-Harbi
Quorum: Four of six members, including Finance
At least 4 voting members needed
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
The summary is available once the meeting has been held and minuted.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-014 · From item 2
Muqawil Platform — Release 4Planned to date 67%
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
PRJ-2026-018 · From item 4
Secure Enterprise NetworkPlanned to date 63%
33 days lateOpen impediments: 1
Agenda item needing a decision · CR-2026-004
Add membership transfer & record mergeFrom item 2
Agenda item needing a decision · CR-2026-012
Add vendor integration capacityFrom item 3
Agenda item needing a decision · CR-2026-014
Re-route the enterprise network in Al-RawdahFrom item 4
Corrective plan awaiting approval · CP-2026-01
Muqawil Platform — Release 4ISS-0103 · Muqawil Platform — Release 4
PeopleSAR 980K· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ISS-0101 · Muqawil Platform — Release 4
Coordination· Asked from: Dr. Abdullah S. Al-Qahtani
A letter from the Secretary-General to the National Information Center for a dedicated test environment for three months
CP-2026-01 · Muqawil Platform — Release 4
PeopleSAR 980K· Asked from: Change Committee
Approve change request CR-2026-012 for three integration engineers
Nothing