CR-2026-012Muqawil Platform — Release 4

Add vendor integration capacity for four months

ResourcesSubmittedImpact level: MinorIn 12 days2026-11-0929 Jumada I 1448 AH

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 980K

Current budgetSAR 86.4M

After the changeSAR 87.4M

+1.1%

Schedule

−⁦12⁩ d
  • Baseline finish2027-03-31
  • New finish2027-03-19

Benefits

+2%

Protects the official launch date

⁦+2⁩% of expected benefits

Reason for change

The vendor is short of integration engineers and the Nafath and Government Service Bus interfaces are late

Justification

Two engineers for four months win back 12 days and lower the project’s top risk

PMO recommendation

Approve

Impact analysis in progress at the PMO

Approval workflow

  1. Submitted

    Eng. Sultan F. Al-Ghamdi

    Done2026-10-26

  2. PM review

    Eng. Sultan F. Al-Ghamdi

    Done2026-10-27

  3. 3

    Impact analysis

    Karim Haddad

    Now2026-10-31

  4. 4

    Finance & procurement

    Munirah A. Al-Khalidi

    Later

  5. 5

    Portfolio manager — capacity

    Faisal A. Al-Shehri

    Later

  6. 6

    PMO approval

    Dr. Noura M. Al-Otaibi

    Later2026-10-29

  7. 7

    Baseline updated

    Eng. Sultan F. Al-Ghamdi

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMinorUp to SAR 1M and no extra days

  • Impact SAR 980K and 0 days — «minor», so the PMO approves it without a committee.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It adds people, so the portfolio manager checks capacity.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

Change Committee — meeting 4229 October 2026 13:00Meeting Room 3 — 5th floor
  • Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saChairNot voted
  • Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.saYouNot voted
  • Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saNot voted
  • Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saNot voted
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@sca.saNot voted
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.saNot voted
0/6⁦4⁩ short of quorum
  • Approve0
  • Approve with conditions0
  • Reject0
  • Abstain0

⁦4⁩ short of quorum · Awaiting the change committee’s decision in meeting ⁦42⁩