PRJ-2026-020Off track4ExecutionConstruction

Qassim Vocational Qualification Centre

Remove from watchlist

A training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 345M

Actual cost

SAR 159.8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 363.2M

SAR +18.2M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
SCA-PMO-F09
Template edition
3.1
Version
V1
Form date
⁦2026-09-28⁩
Hijri
17 Rabiʻ II 1448 AH
In approvalCR-2026-010Redesign the foundations of axes 12 to 16

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-020
Project
Qassim Vocational Qualification Centre
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Ahmed Y. Asiri

1The change

TitleAuto-filled
Redesign the foundations of axes 12 to 16
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Ahmed Y. Asiri
Raised onAuto-filled
⁦2026-09-28⁩

Reason

Unforeseen ground at axes 12 to 16

Justification

The current design misses the required safety factor

2Impact analysis

Cost

SAR +8.4M

Schedule

+55 days

Risk

20 → 8

Benefits

0%

Risk impact

Treats the centre’s critical risk

Benefits impact

No effect on benefits

3The approval decision

The PMO’s recommendation

The PMO recommends urgent approval: every day of delay costs SAR 150K

Change Committee decision
Not taken yet
Decided on
—
Decision number
—

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ahmed Y. AsiriDirector, Construction ProjectsSubmitted—⁦2026-09-28⁩ 10:49
2Project managerTechnical acceptanceEng. Ahmed Y. AsiriProject managerApproved—⁦2026-09-29⁩ 12:03
3PMO review & impact analysisMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-09-30⁩ 13:10
4Financial impactFinancial approvalApproval engineFinancePre-breach alert—⁦2026-10-04⁩ 08:00

Signatures

Project manager

Eng. Ahmed Y. Asiri

Approved⁦2026-09-29⁩

PMO review & impact analysis

Ghada A. Al-Shahrani

Approved⁦2026-09-30⁩

Financial impact

Munirah A. Al-Khalidi

Awaiting decision

Contractual impact

Mazen A. Al-Hazmi

Later

Change Committee

Dr. Mohammed I. Al-Subaie

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F09 · version V1

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Ahmed Y. Asiri on ⁦2026-09-28⁩

  1. Technical acceptance

    Project manager

    Eng. Ahmed Y. Asiri · Project manager

    Approved · ⁦2026-09-29⁩ at ⁦12:03⁩

  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-09-30⁩ at ⁦13:10⁩

  3. Financial approval

    Financial impact

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    18 working days overdueAction time limit exceeded · Limit 2 working daysLimit 2 working days · Due ⁦2026-10-04⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-04⁩

    Waiting on Khalid N. Al-Mutairi
  4. Financial approval

    Contractual impact

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Limit 2 working days · Expected by ⁦2026-10-06⁩

  5. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Delegated to Dr. Noura M. Al-Otaibi

    Limit 3 working days · Expected by ⁦2026-10-11⁩

Steps that do not apply to this record

  • Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-09-28⁩

    The request as raised

    Eng. Ahmed Y. Asiri

Only one version so far.