CR-2026-016Muqawil Mobile App — Release 3
Bring the model contracts into the app’s first release
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
+SAR 320KCurrent budgetSAR 12.6M
After the changeSAR 12.9M
+2.5%
Schedule
+10 d- Baseline finish2027-01-31
- New finish2027-02-10
Risk
+3Loads the shared team further
Benefits
+4%15% more expected app downloads
+4% of expected benefits
Reason for change
A request to put the model contracts into the app’s first release
Justification
Model contracts are among the services member contractors use most
PMO recommendation
DeferThe PMO recommends deferring to release 2
Approval workflow
Submitted
Karim Haddad
Done2026-09-14
PM review
Karim Haddad
Done2026-09-15
Impact analysis
Karim Haddad
Done2026-09-19
Finance & procurement
Munirah A. Al-Khalidi
Done2026-09-20
Project owner’s acceptance
Faisal A. Al-Shehri
Done2026-09-20
- 6
Change committee decision
Dr. Mohammed I. Al-Subaie
Deferred2026-09-29
Baseline updated
Karim Haddad
N/A
Why this route
The route is built from the request’s kind and impact level under the approved authority matrix.
Impact levelModerateUp to SAR 5M and 90 days
- Impact SAR 320K and 10 days — «moderate», so the Change Committee decides.
- It has a financial link, so Finance & Procurement take part before the decision.
- It changes scope or deliverables, so the project owner must accept it.
Change committee vote
Members vote before or during the meeting; the decision is taken once quorum is met
- Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saChairApprove with conditions
- Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.saYouApprove with conditions
- Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saApprove
- Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saApprove with conditions
- Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@sca.saApprove with conditions
- Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.saApprove with conditions
- Approve1
- Approve with conditions5
- Reject0
- Abstain0
Decided by the committee on 29 September 2026The decision in the log · DEC-2026-027