CR-2026-016Muqawil Mobile App — Release 3

Bring the model contracts into the app’s first release

DeliverablesDeferredImpact level: Moderate

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 320K

Current budgetSAR 12.6M

After the changeSAR 12.9M

+2.5%

Schedule

+⁦10⁩ d
  • Baseline finish2027-01-31
  • New finish2027-02-10

Benefits

+4%

15% more expected app downloads

⁦+4⁩% of expected benefits

Reason for change

A request to put the model contracts into the app’s first release

Justification

Model contracts are among the services member contractors use most

PMO recommendation

Defer

The PMO recommends deferring to release 2

Approval workflow

  1. Submitted

    Karim Haddad

    Done2026-09-14

  2. PM review

    Karim Haddad

    Done2026-09-15

  3. Impact analysis

    Karim Haddad

    Done2026-09-19

  4. Finance & procurement

    Munirah A. Al-Khalidi

    Done2026-09-20

  5. Project owner’s acceptance

    Faisal A. Al-Shehri

    Done2026-09-20

  6. 6

    Change committee decision

    Dr. Mohammed I. Al-Subaie

    Deferred2026-09-29

  7. Baseline updated

    Karim Haddad

    N/A

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelModerateUp to SAR 5M and 90 days

  • Impact SAR 320K and 10 days — «moderate», so the Change Committee decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

  • Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saChairApprove with conditions
  • Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.saYouApprove with conditions
  • Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saApprove
  • Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saApprove with conditions
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@sca.saApprove with conditions
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.saApprove with conditions
6/6Quorum met
  • Approve1
  • Approve with conditions5
  • Reject0
  • Abstain0

Decided by the committee on 29 September 2026The decision in the log · DEC-2026-027