PRJ-2026-015On track4ExecutionScrum

Muqawil Mobile App — Release 3

Add to watchlist

A mobile app for contractors’ most-used services, with instant renewal alerts and a digital wallet for the membership card and certificates.

Budget (BAC)

SAR 12.6M

Actual cost

SAR 7.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 12.1M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+4

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦64%⁩ done against ⁦63%⁩ planned.

SPI ⁦1.02⁩, CPI ⁦1.04⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Unified Reference for Regulating the SectorSO-1.1Simplify regulatory relationships and make doing business easier

Main initiative

SI-1.1.1One digital journey for contractors

Contribution to the initiative⁦12%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-015
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦64%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦26%⁩

6 deliverables accepted

  • Release 1⁦16%⁩
  • Release 2⁦16%⁩
  • Business requirements⁦11%⁩
  • Solution design⁦11%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦5%⁩

1 deliverable under inspection or acceptance

  • Integrations⁦10%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦87%⁩ of budget

7.8M/ 12.6M485Kprojected saving(⁦3.8%⁩)
Actual spend
7.8M
Committed
10.9M
Approved budget
12.6M
Estimate at completion
12.1M

Next milestones

  • Provisional acceptance⁦2026-12-21⁩was ⁦2026-12-23⁩On track
  • Closure⁦2027-01-28⁩was ⁦2027-01-31⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Risks & impediments

0 open risks, exposure SAR 0

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Top risks

  • No open risks

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦6⁩ of ⁦11⁩ approved

  • Project plan & baseline015-D1 · V1 · CRT-015-01⁦5%⁩Karim Haddad⁦2025-12-11⁩2025-12-1120 Jumada II 1447 AHApproved
  • Monitoring & reporting015-D2 · V1 · CRT-015-02⁦5%⁩Faisal A. Al-Shehri⁦2026-01-21⁩2026-01-212 Shaʻban 1447 AHApproved
  • Business requirements015-D3 · V1 · CRT-015-03⁦11%⁩Faisal A. Al-Shehri⁦2026-03-04⁩2026-03-0415 Ramadan 1447 AHApproved
  • Solution design015-D4 · V1 · CRT-015-04⁦11%⁩Eng. Majed S. Al-Rasheed⁦2026-04-15⁩2026-04-1527 Shawwal 1447 AHApproved
  • Release 1015-D5 · V1 · CRT-015-05⁦16%⁩Eng. Majed S. Al-Rasheed⁦2026-05-26⁩2026-05-269 Dhuʻl-Hijjah 1447 AHApproved
  • Release 2015-D6 · V1 · CRT-015-06⁦16%⁩Karim Haddad⁦2026-07-07⁩2026-07-0722 Muharram 1448 AHApproved
  • Integrations015-D7 · V1⁦10%⁩Faisal A. Al-Shehri72 days overdue2026-08-174 Rabiʻ I 1448 AHIn review
  • System testing015-D8 · V0⁦7%⁩Karim Haddad30 days overdue2026-09-2817 Rabiʻ II 1448 AHDraft
  • User acceptance testing015-D9 · V0⁦7%⁩Faisal A. Al-ShehriIn 12 days2026-11-0929 Jumada I 1448 AHDraft
  • Training & change015-D10 · V0⁦6%⁩Faisal A. Al-ShehriIn 53 days2026-12-2011 Rajab 1448 AHDraft
  • Go-live & handover015-D11 · V0⁦6%⁩Eng. Majed S. Al-RasheedIn 95 days2027-01-3123 Shaʻban 1448 AHDraft

Team, contracts & documents

Team

7 members

Karim Haddad · Senior Digital Delivery Consultant — PMOEng. Reem K. Al-Dosari · Head of the Muqawil Platform & Programme Manager, Muqawil & e-ServicesBadr N. Al-Haqbani · Director General, Membership & Contractor ServicesJoud N. Al-Ahmadi · QA & Testing SpecialistHussam T. Al-Qurashi · Senior Software Engineer – IntegrationLama S. Al-Harbi · Senior Business Analyst — Contractor Services
  • Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOProject managerP-041k.haddad@sca.sa⁦40%⁩
  • Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the Muqawil Platform & Programme Manager, Muqawil & e-ServicesProgramme oversight, mobile appP-004r.aldosari@sca.sa⁦15%⁩
  • Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & Contractor ServicesProject ownerP-046b.alhaqbani@sca.sa⁦5%⁩
  • Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistApp testingP-033j.alahmadi@sca.sa⁦40%⁩
  • Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationApp APIs to MuqawilP-030h.alqurashi@sca.sa⁦35%⁩
  • Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Contractor ServicesApp service requirementsP-006l.alharbi@sca.sa⁦25%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close