Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-015On track4ExecutionScrum

Muqawil Mobile App — Release 3

Add to watchlist

A mobile app for contractors’ most-used services, with instant renewal alerts and a digital wallet for the membership card and certificates.

Budget (BAC)

SAR 12.6M

Actual cost

SAR 7.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 12.1M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2027-01-31⁩
    Budget
    SAR 12.6M
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-10-05⁩ · by Eng. Majed S. Al-Rasheed

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-01-31⁩
    Budget
    SAR 12.6M
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Karim Haddad

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2027-01-31⁩⁦2027-01-31⁩

⁦0⁩ days

Budget

SAR 12.6MSAR 12.6M

⁦0.00⁩ SAR M

Milestones moved

4 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-072027-01
  • Project plan approved⁦+45⁩
  • Designs approved⁦+78⁩
  • Build complete⁦+86⁩
  • Testing & acceptance complete⁦+40⁩
  • Final handover

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦−0.00⁩
  • 2Analysis & design⁦−0.00⁩
  • 3Build⁦+0.24⁩
  • 4Testing & acceptance⁦−0.16⁩
  • 5Launch & handover⁦−0.12⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Karim Haddad
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-10-05⁩by Eng. Majed S. Al-Rasheed
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close