PRJ-2026-015On track4ExecutionScrum

Muqawil Mobile App — Release 3

Add to watchlist

A mobile app for contractors’ most-used services, with instant renewal alerts and a digital wallet for the membership card and certificates.

Budget (BAC)

SAR 12.6M

Actual cost

SAR 7.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 12.1M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 12.6M split into spent, committed and left, with the estimate at completion

EAC SAR 12.1M
Revised request SAR 12.6M
  • Actual spendSAR 7.8M
  • Committed, not spentSAR 3.1M
  • Allotted, uncommittedSAR 1.3M
  • Contingency availableSAR 378K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 12.2M
Original budgetwhen the first baseline was approved
SAR 12.6M
Approved budgetafter approved change requests
SAR 12.6M
Current budgetavailable to spend now
SAR 12.6M
Revised budgetif the pending changes are approved
SAR 12.6M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 10.9M
Contracts1 active contract
SAR 9.8M
Purchase orders⁦2⁩ orders
SAR 1.1M
Remaining budgetapproved less actual
SAR 4.8M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 7.8M
Accrualswork done, not yet invoiced
SAR 310K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 12.1M
ContingencySAR 252K drawn of SAR 630K
SAR 378K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 12.2M
ApprovedSAR 12.6M
Estimate at completionSAR 12.1M
Approved is SAR 400K (⁦3.3%⁩) above the estimate
The estimate at completion is SAR 85K (⁦0.7%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-07-22⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-41015
  • WBS elements⁦5⁩ elements · P-2026-015.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦8⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 252K drawn of SAR 630K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 252K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.980.980.970.98⁦+0.00⁩
2Analysis & design2.082.072.062.08⁦+0.00⁩
3Build4.894.844.724.88⁦+0.01⁩
4Testing & acceptance2.441.720.002.28⁦+0.16⁩
5Launch & handover1.831.290.001.71⁦+0.12⁩
Unallocated contingency0.380.000.000.19⁦+0.19⁩
Total12.6010.907.7512.12⁦+0.49⁩

Budget split

WBS

SAR 12.6M

Budget

  • Management & governanceSAR 977.8K⁦8%⁩
  • Analysis & designSAR 2.1M⁦16%⁩
  • BuildSAR 4.9M⁦39%⁩
  • Testing & acceptanceSAR 2.4M⁦19%⁩
  • Launch & handoverSAR 1.8M⁦15%⁩
  • Unallocated contingencySAR 378K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-07-27⁩+177

SPI(t) ⁦0.73⁩ against the approved finish ⁦2027-01-31⁩

Planned valuePV
SAR 11.4M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 8.1M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 7.8M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 12.6M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.31⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−3.37⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.04
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.71
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 12.1M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 4.4M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.49⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.94
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 12.1M
  • If the rest goes to planSAR 12.3M
  • At cost and schedule performanceSAR 13.9M
  • The PM’s bottom-up estimateSAR 12.1M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 12.1M

Variance at completion: ⁦+0.48⁩ SAR M