Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-015On track4ExecutionScrum

Muqawil Mobile App — Release 3

Add to watchlist

A mobile app for contractors’ most-used services, with instant renewal alerts and a digital wallet for the membership card and certificates.

Budget (BAC)

SAR 12.6M

Actual cost

SAR 7.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 12.1M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work12.2M⁦16⁩ elements
Unallocated contingency378KSAR 630K
Budget at completion12.6MPRJ-2026-015
Weighted progress⁦64%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project483⁦2025-10-05⁩⁦2027-01-31⁩⁦64%⁩12.227.75—
1
Phase153⁦2025-10-05⁩⁦2026-03-07⁩⁦100%⁩0.980.97—
1.1
WBS element94⁦2025-10-05⁩⁦2026-01-07⁩⁦100%⁩0.490.490 / 1
1.2
WBS element94⁦2025-12-03⁩⁦2026-03-07⁩⁦100%⁩0.490.491 / 2
2
Phase153⁦2026-01-30⁩⁦2026-07-02⁩⁦100%⁩2.082.06—
2.1
WBS element94⁦2026-01-30⁩⁦2026-05-04⁩⁦100%⁩1.041.031 / 1
2.2
WBS element94⁦2026-03-30⁩⁦2026-07-02⁩⁦100%⁩1.041.031 / 2
3
Phase167⁦2026-05-28⁩⁦2026-11-11⁩⁦97%⁩4.894.72—
3.1
WBS element94⁦2026-05-28⁩⁦2026-08-30⁩⁦100%⁩1.631.621 / 1
3.2
WBS element92⁦2026-07-26⁩⁦2026-10-26⁩⁦100%⁩1.631.621 / 1
3.3
WBS element152⁦2026-06-12⁩⁦2026-11-11⁩⁦92%⁩1.631.491 / 2
4
Phase50⁦2026-10-30⁩⁦2026-12-19⁩⁦0%⁩2.44——
4.1
WBS element31⁦2026-10-30⁩⁦2026-11-30⁩⁦0%⁩1.22—1 / 1
4.2
WBS element31⁦2026-11-18⁩⁦2026-12-19⁩⁦0%⁩1.22—1 / 2
5
Phase55⁦2026-12-07⁩⁦2027-01-31⁩⁦0%⁩1.83——
5.1
WBS element31⁦2026-12-07⁩⁦2027-01-07⁩⁦0%⁩0.92—1 / 1
5.2
WBS element31⁦2026-12-26⁩⁦2027-01-26⁩⁦0%⁩0.92—1 / 1
Total⁦64%⁩12.227.75
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close