Muqawil Mobile App — Release 3 Subtask Last item under this branch 2027-01-31 64% Muqawil Mobile App — Release 3 Planned: 2025-10-05 → 2027-01-31 Forecast: 2025-10-05 → 2027-01-31 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-03-07 100% Management & governance Planned: 2025-10-05 → 2026-01-21 Actual: 2025-10-05 → 2026-03-07
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-01-07 100% Project plan & baseline Planned: 2025-10-05 → 2025-12-11 Actual: 2025-10-05 → 2026-01-07
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-07 100% Monitoring & reporting Planned: 2025-11-16 → 2026-01-21 Actual: 2025-12-03 → 2026-03-07
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-07 100% Project plan approved Planned: 2026-01-21 → 2026-01-21 Actual: 2026-03-07 → 2026-03-07 Project plan approved
2 Analysis & design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-07-02 100% Analysis & design Planned: 2025-12-27 → 2026-04-15 Actual: 2026-01-30 → 2026-07-02
2.1 Business requirements Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-04 100% Business requirements Planned: 2025-12-27 → 2026-03-04 Actual: 2026-01-30 → 2026-05-04
2.2 Solution design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-02 100% Solution design Planned: 2026-02-07 → 2026-04-15 Actual: 2026-03-30 → 2026-07-02
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-02 100% Designs approved Planned: 2026-04-15 → 2026-04-15 Actual: 2026-07-02 → 2026-07-02 Designs approved
3 Build Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-11-11 97% Build Planned: 2026-03-21 → 2026-08-17 Forecast: 2026-05-28 → 2026-11-11 Float: 5d
3.1 Release 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-30 100% Release 1 Planned: 2026-03-21 → 2026-05-26 Actual: 2026-05-28 → 2026-08-30
3.2 Release 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Release 2 Planned: 2026-05-01 → 2026-07-07 Actual: 2026-07-26 → 2026-10-26
3.3 Integrations Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-11 92% Integrations Planned: 2026-06-12 → 2026-08-17 Forecast: 2026-06-12 → 2026-11-11 Float: 5d Drag to change its duration +86
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-11 0% Build complete Planned: 2026-08-17 → 2026-08-17 Forecast: 2026-11-11 → 2026-11-11 Float: 81d Drag to change its dates Build complete
4 Testing & acceptance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-12-19 0% Testing & acceptance Planned: 2026-07-23 → 2026-11-09 Forecast: 2026-10-30 → 2026-12-19 Float: 5d
4.1 System testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-30 0% System testing Planned: 2026-07-23 → 2026-09-28 Forecast: 2026-10-30 → 2026-11-30 Float: 5d Drag to change its dates +63
4.2 User acceptance testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-19 0% User acceptance testing Planned: 2026-09-03 → 2026-11-09 Forecast: 2026-11-18 → 2026-12-19 Float: 5d Drag to change its dates +40
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-19 0% Testing & acceptance complete Planned: 2026-11-09 → 2026-11-09 Forecast: 2026-12-19 → 2026-12-19 Float: 43d Drag to change its dates Testing & acceptance complete
5 Launch & handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-31 0% Launch & handover Planned: 2026-10-15 → 2027-01-31 Forecast: 2026-12-07 → 2027-01-31 Float: 0d
5.1 Training & change Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-07 0% Training & change Planned: 2026-10-15 → 2026-12-20 Forecast: 2026-12-07 → 2027-01-07 Float: 5d Drag to change its dates +18
5.2 Go-live & handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-26 0% Go-live & handover Planned: 2026-11-25 → 2027-01-31 Forecast: 2026-12-26 → 2027-01-26 Float: 5d Drag to change its dates
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-31 0% Final handover Planned: 2027-01-31 → 2027-01-31 Forecast: 2027-01-31 → 2027-01-31 Float: 0d Drag to change its dates Final handover