CR-2026-013SCA Backup Data Centre

Replace the cooling-unit supplier

ContractApprovedImpact level: Moderate

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 3.1M

Current budgetSAR 144.9M

After the changeSAR 148M

+2.1%

Schedule

+⁦14⁩ d
  • Baseline finish2026-11-16
  • New finish2026-11-30

Risk

−4

Benefits

+2%

8% better energy efficiency

⁦+2⁩% of expected benefits

Reason for change

The original cooling supplier defaulted

Justification

The alternative delivers in 14 weeks with a longer warranty

PMO recommendation

Approve

The PMO recommends approval

Approval workflow

  1. Submitted

    Eng. Omar H. Bawazir

    Done2026-05-17

  2. PM review

    Eng. Omar H. Bawazir

    Done2026-05-18

  3. Impact analysis

    Karim Haddad

    Done2026-05-22

  4. Finance & procurement

    Munirah A. Al-Khalidi

    Done2026-05-23

  5. Change committee decision

    Dr. Mohammed I. Al-Subaie

    Done2026-05-28

  6. Baseline updated

    Eng. Omar H. Bawazir

    Done2026-06-01

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelModerateUp to SAR 5M and 90 days

  • Impact SAR 3.1M and 14 days — «moderate», so the Change Committee decides.
  • It touches a signed contract, so Finance & Procurement review it contractually.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

  • Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saChairApprove
  • Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.saYouApprove
  • Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saApprove
  • Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saApprove
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@sca.saApprove
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.saApprove
6/6Quorum met
  • Approve6
  • Approve with conditions0
  • Reject0
  • Abstain0

Decided by the committee on 28 May 2026The decision in the log · DEC-2026-014

Baseline

Baseline updated on 1 June 2026