Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-003At risk4ExecutionWaterfall

SCA Backup Data Centre

Add to watchlist

A Tier III backup data centre in Dammam that keeps Muqawil and the Authority’s systems running and recovers them after a disaster.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 148M

Actual cost

SAR 117.1M

⁦79%⁩ of budget

Progress

⁦72%⁩Awaiting acceptance ⁦8%⁩

Estimate at completion

SAR 162.6M

SAR +14.6M

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-11-30⁩
    Budget
    SAR 144.9M
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-04-06⁩ · by Eng. Majed S. Al-Rasheed

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-01-09⁩
    ⁦+40⁩ days
    Budget
    SAR 148M
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Omar H. Bawazir

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-11-30⁩⁦2027-01-09⁩

⁦+40⁩ days

Budget

SAR 144.9MSAR 148M

⁦+3.10⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-012026-072027-01
  • Project plan approved⁦+60⁩
  • Designs approved⁦+106⁩
  • Build complete⁦+173⁩
  • Testing & acceptance complete⁦+112⁩
  • Final handover⁦+40⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+1.53⁩
  • 2Analysis & design⁦+3.24⁩
  • 3Build⁦+10.59⁩
  • 4Testing & acceptance⁦+1.99⁩
  • 5Launch & handover⁦+2.47⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Omar H. Bawazir
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-04-06⁩by Eng. Majed S. Al-Rasheed
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close