SCA Backup Data Centre
Add to watchlistA Tier III backup data centre in Dammam that keeps Muqawil and the Authority’s systems running and recovers them after a disaster.
Budget (BAC)
Actual cost
79% of budget
Progress
Estimate at completion
SAR +14.6M
SPI · CPI
Forecast finish
38 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Initiation»DecisionGoDate5 February 2025All criteria and required documents met.Pre-startComplete
- Gate into «Planning»DecisionConditional goDate6 April 2025Mandatory criteria met, with points to close during the next phase.InitiationComplete
- Gate into «Execution»DecisionConditional goDate11 July 2025Mandatory criteria met, with points to close during the next phase.PlanningComplete
- Gate into «Closure»DecisionNot held yetDate13 October 2026ExecutionCurrent stageCurrent stage
- 5ClosureNot started
What each stage requires
The documents and approvals each gate asks for before the next stage.
Closure gate — deliverables accepted and handed over
Gate readiness
Meets the pass mark
Automated control: no move until the criteria are met
- 1 mandatory checklist item open
- 2 required documents not approved
- 1 mandatory criterion under 70 points
Checklist
5 of 7 done
- Deliverable completion certificates approved for every deliverableMandatory
- Acceptance tests and handover to operations completeMandatory
- Open commitments listed with a plan to close themMandatory
- Deliverable-linked payments settledMandatory
- Pilot run with no critical or high findingsMandatory
- Users trained
- Launch rollback plan
Required documents
2 of 4 approved
- Deliverable completion certificatesNot submitted
- Project closure & handover formApproved · V1
- Lessons-learned logApproved · V1
- Benefits measurement planNot submitted
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables acceptedweight 35%Met
Awaiting evidence from the project team.
Quality & securityweight 25%Not met
Awaiting evidence from the project team.
Operations & handover readinessweight 25%Met
Awaiting evidence from the project team.
User & training readinessweight 15%
Awaiting evidence from the project team.
Approvers
Project Management Office
- Dr. Noura M. Al-OtaibiPMO directorVote pending
- Eng. Nayef H. Al-BuqamiProject ownerVote pending
- Eng. Majed S. Al-RasheedProject sponsorVote pending