1SCA-PMO-F01Proposal
Project proposal & feasibility study
Justification, objectives, benefits, cost and initial risks
A Tier III backup data centre in Dammam that keeps Muqawil and the Authority’s systems running and recovers them after a disaster.
Budget (BAC)
Actual cost
79% of budget
Progress
Estimate at completion
SAR +14.6M
SPI · CPI
Forecast finish
38 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 October 2026
The project’s twelve forms with their status and approval path, each printable with its approval log.
Forms
18In approval
1Past their limit
1Escalated automatically
0Approved
161SCA-PMO-F01Proposal
Justification, objectives, benefits, cost and initial risks
2SCA-PMO-F02Proposal
Criteria, weights and the P1–P4 result
3SCA-PMO-F03Approval
The weight and the relative weight in the portfolio
4SCA-PMO-F04Initiation
Objective, scope, deliverables, roles and budget
5SCA-PMO-F05Planning
Schedule, deliverables, risks, communications, quality and benefits
6SCA-PMO-F06Planning
Roles, tasks, decisions and the start of execution
7SCA-PMO-F07Execution
Progress, status, risks and support requested
8SCA-PMO-F08Execution
Evidence, inspection, acceptance and the financial link
8 copies
9SCA-PMO-F09Execution
The change, its impact analysis and the approval decision
10SCA-PMO-F10Execution
The decision, the rationale and the approvals
Not yet · Opens at the «Execution» stage
11SCA-PMO-F11Execution
Actions, owners, dates and status
Not yet · Opens at the «Execution» stage
12SCA-PMO-F12Closure
Performance, handover, open commitments and lessons learned
Not yet · Opens at the «Closure» stage