Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-003At risk4ExecutionWaterfall

SCA Backup Data Centre

Add to watchlist

A Tier III backup data centre in Dammam that keeps Muqawil and the Authority’s systems running and recovers them after a disaster.

Early warning: ⁦63%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 148M

Actual cost

SAR 117.1M

⁦79%⁩ of budget

Progress

⁦72%⁩Awaiting acceptance ⁦8%⁩

Estimate at completion

SAR 162.6M

SAR +14.6M

SPI · CPI

0.90Schedule performance index · 0.900.91Cost performance index · 0.91

Forecast finish

⁦2027-01-07⁩

38 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 February 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate6 April 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate11 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 October 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-01-01⁩
Hijri
12 Rajab 1447 AH
ApprovedCRT-003-03Business requirements

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-003
Project
SCA Backup Data Centre
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Omar H. Bawazir

1The deliverableAuto-filled

DeliverableAuto-filled
Business requirements
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Nayef H. Al-Buqami
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦9%⁩
DueAuto-filled
⁦2025-10-10⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-003_2.1_v1.pdfV1Eng. Nayef H. Al-Buqami⁦2025-09-03⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Nayef H. Al-Buqami
Accepted byAuto-filled
Eng. Majed S. Al-Rasheed
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
CTR-2025-006
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Nayef H. Al-BuqamiDirector General, Information TechnologySubmitted—⁦2025-09-03⁩ 09:48
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-09-04⁩ 13:04
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Majed S. Al-RasheedProject ownerOn behalf of Eng. Nayef H. Al-BuqamiApprovedInspected and accepted against the approved acceptance criteria.⁦2025-09-09⁩ 14:11
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-09-11⁩ 12:51
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-09-14⁩ 13:28

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-09-04⁩

Inspection & technical acceptance — owner

Eng. Majed S. Al-Rasheed

Approved⁦2025-09-09⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-09-11⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-09-14⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Nayef H. Al-Buqami on ⁦2025-09-03⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-09-04⁩ at ⁦13:04⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Nayef H. Al-Buqami · Project owner

    Approved · ⁦2025-09-09⁩ at ⁦14:11⁩ · On behalf of Eng. Nayef H. Al-Buqami (Eng. Majed S. Al-Rasheed)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-09-11⁩ at ⁦12:51⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-14⁩ at ⁦13:28⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-09-03⁩

    PRJ-2026-003_2.1_v1.pdf

    Eng. Nayef H. Al-Buqami

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close