CR-2026-015Correspondence & Document Management System (DMS)

Add a classified-correspondence module

DeliverablesRejectedImpact level: Moderate

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 650K

Current budgetSAR 14.2M

After the changeSAR 14.9M

+4.6%

Schedule

+⁦30⁩ d
  • Baseline finish2026-09-30
  • New finish2026-10-30

Risk

+6
9Medium15High

Adds heavy security requirements at handover

Benefits

+1%

Limited: under 2% of correspondence

⁦+1⁩% of expected benefits

Reason for change

A request to add a classified-correspondence module

Justification

Classified correspondence is handled on paper today

PMO recommendation

Reject

The PMO recommends rejection; run the module as its own project

Approval workflow

  1. Submitted

    Dana S. Al-Saleh

    Done2026-08-11

  2. PM review

    Dana S. Al-Saleh

    Done2026-08-12

  3. Impact analysis

    Karim Haddad

    Done2026-08-16

  4. Finance & procurement

    Munirah A. Al-Khalidi

    Done2026-08-17

  5. Project owner’s acceptance

    Munirah A. Al-Khalidi

    Done2026-08-17

  6. Change committee decision

    Dr. Mohammed I. Al-Subaie

    Rejected2026-08-25

  7. Baseline updated

    Dana S. Al-Saleh

    N/A

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelModerateUp to SAR 5M and 90 days

  • Impact SAR 650K and 30 days — «moderate», so the Change Committee decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

  • Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saChairReject
  • Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.saYouReject
  • Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saReject
  • Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saReject
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@sca.saAbstain
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.saReject
6/6Quorum met
  • Approve0
  • Approve with conditions0
  • Reject5
  • Abstain1

Decided by the committee on 25 August 2026The decision in the log · DEC-2026-023