PRJ-2026-017At risk5ClosureWaterfall

Correspondence & Document Management System (DMS)

Add to watchlist

Automated correspondence, document management and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Change request

The change, its impact analysis and the approval decision

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
SCA-PMO-F09
Template edition
3.1
Version
V1
Form date
⁦2026-08-11⁩
Hijri
28 Safar 1448 AH
RejectedCR-2026-015Add a classified-correspondence module

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-017
Project
Correspondence & Document Management System (DMS)
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The change

TitleAuto-filled
Add a classified-correspondence module
KindAuto-filled
Deliverables
Requested byAuto-filled
Dana S. Al-Saleh
Raised onAuto-filled
⁦2026-08-11⁩

Reason

A request to add a classified-correspondence module

Justification

Classified correspondence is handled on paper today

2Impact analysis

Cost

SAR +650K

Schedule

+30 days

Risk

9 → 15

Benefits

+1%

Risk impact

Adds heavy security requirements at handover

Benefits impact

Limited: under 2% of correspondence

3The approval decision

The PMO’s recommendation

The PMO recommends rejection; run the module as its own project

Change Committee decision
Reject
Decided on
⁦2026-08-25⁩
Decision number
DEC-2026-023

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2026-08-11⁩ 09:24
2Project managerTechnical acceptanceDana S. Al-SalehProject managerApproved—⁦2026-08-12⁩ 11:08
3PMO review & impact analysisMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-08-16⁩ 12:15
4Financial impactFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-08-18⁩ 10:43
5Change CommitteeTechnical acceptanceDr. Mohammed I. Al-SubaieChange CommitteeRejected—⁦2026-08-19⁩ 09:36

Signatures

Project manager

Dana S. Al-Saleh

Approved⁦2026-08-12⁩

PMO review & impact analysis

Ghada A. Al-Shahrani

Approved⁦2026-08-16⁩

Financial impact

Munirah A. Al-Khalidi

Approved⁦2026-08-18⁩

Change Committee

Dr. Mohammed I. Al-Subaie

Rejected⁦2026-08-19⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F09 · version V1

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Dana S. Al-Saleh on ⁦2026-08-11⁩

  1. Technical acceptance

    Project manager

    Dana S. Al-Saleh · Project manager

    Approved · ⁦2026-08-12⁩ at ⁦11:08⁩

  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-08-16⁩ at ⁦12:15⁩

  3. Financial approval

    Financial impact

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-08-18⁩ at ⁦10:43⁩

  4. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Delegated to Dr. Noura M. Al-Otaibi

    Rejected · ⁦2026-08-19⁩ at ⁦09:36⁩

Steps that do not apply to this record

  • Contractual impact — the condition «Contract link?» does not hold
  • Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

The form was rejected and its path closed.

Previous versions

Every version is kept with its status and what changed.

  1. V1RejectedCurrent⁦2026-08-11⁩

    The request as raised

    Dana S. Al-Saleh

Only one version so far.