PRJ-2026-017At risk5ClosureWaterfall

Correspondence & Document Management System (DMS)

Add to watchlist

Automated correspondence, document management and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦0⁩ of ⁦9⁩ mandatory documents due
  • 9 mandatory documents missing
  • 1 document in the repository

The project is in its closure stage

Once the closure & handover form is approved, the project’s documents move to the archive, read-only.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3Planning
    • Project management plan, schedule & baselineMandatory· Missing

      Planning gate G3

    • Contract or purchase orderMandatory· Missing

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Missing

      Project management plan

  4. 4Execution
    • Periodic update cards & status reportsMandatory· Missing

      Periodic update card form

    • Deliverable completion certificatesMandatory· Missing

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Missing

      Corrective plan form

  5. 5ClosureCurrent stage
    • Project closure & handover formMandatory· Missing

      Closure gate G4

    • Lessons learnedMandatory· Missing

      Closure gate G4

    • Acceptance test resultsOptional· Present

      UAT results — correspondence platformV2

      Deliverable acceptance

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 017-D1Project plan & baselinePRJ-2026-017_1.1_v1.pdfApprovedDeliverable
  • 017-D2Monitoring & reportingPRJ-2026-017_1.2_v1.pdfApprovedDeliverable
  • 017-D3Business requirementsPRJ-2026-017_2.1_v1.pdfApprovedDeliverable
  • 017-D4Solution designPRJ-2026-017_2.2_v1.pdfApprovedDeliverable
  • 017-D5Release 1PRJ-2026-017_3.1_v1.pdfApprovedDeliverable
  • 017-D6Release 2PRJ-2026-017_3.2_v1.pdfApprovedDeliverable
  • 017-D7IntegrationsPRJ-2026-017_3.3_v1.pdfApprovedDeliverable
  • 017-D8System testingPRJ-2026-017_4.1_v1.pdfApprovedDeliverable
  • 017-D9User acceptance testingPRJ-2026-017_4.2_v1.pdfApprovedDeliverable
  • 017-D10Training & changePRJ-2026-017_5.1_v1.pdfApprovedDeliverable
  • 017-D11Go-live & handoverPRJ-2026-017_5.2_v1.pdfIn reviewDeliverable