Correspondence & Document Management System (DMS)
Add to watchlistAutomated correspondence, document management and e-archiving, linked to the government communications network.
Budget (BAC)
Actual cost
95% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
46 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage
Project documents by stage
What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.
Mandatory complete
0
of 9
- 0 of 9 mandatory documents due
- 9 mandatory documents missing
- 1 document in the repository
The project is in its closure stage
Once the closure & handover form is approved, the project’s documents move to the archive, read-only.
Stages and required documents
For each of the five stages, what its gates and forms require: present, missing, or not yet due.
- 1Pre-start
Project proposal & feasibility studyMandatory· Missing
Approval gate G1
Priority & weight assessmentOptional· Missing
Annual work plan
- 2Initiation
Approved project charterMandatory· Missing
Initiation gate G2
Kick-off meeting minutesMandatory· Missing
Initiation gate G2
- 3Planning
Project management plan, schedule & baselineMandatory· Missing
Planning gate G3
Contract or purchase orderMandatory· Missing
Finance & procurement — when there is a contract
Technical studies & drawingsOptional· Missing
Project management plan
- 4Execution
Periodic update cards & status reportsMandatory· Missing
Periodic update card form
Deliverable completion certificatesMandatory· Missing
Deliverable completion certificate form
Corrective plan when off trackOptional· Missing
Corrective plan form
- 5ClosureCurrent stage
Project closure & handover formMandatory· Missing
Closure gate G4
Lessons learnedMandatory· Missing
Closure gate G4
Acceptance test resultsOptional· Present
UAT results — correspondence platformV2Deliverable acceptance
Evidence tied to deliverables
Each deliverable with its repository document and the files that prove it.
- 017-D1Project plan & baselinePRJ-2026-017_1.1_v1.pdfApprovedDeliverable
- 017-D2Monitoring & reportingPRJ-2026-017_1.2_v1.pdfApprovedDeliverable
- 017-D3Business requirementsPRJ-2026-017_2.1_v1.pdfApprovedDeliverable
- 017-D4Solution designPRJ-2026-017_2.2_v1.pdfApprovedDeliverable
- 017-D5Release 1PRJ-2026-017_3.1_v1.pdfApprovedDeliverable
- 017-D6Release 2PRJ-2026-017_3.2_v1.pdfApprovedDeliverable
- 017-D7IntegrationsPRJ-2026-017_3.3_v1.pdfApprovedDeliverable
- 017-D8System testingPRJ-2026-017_4.1_v1.pdfApprovedDeliverable
- 017-D9User acceptance testingPRJ-2026-017_4.2_v1.pdfApprovedDeliverable
- 017-D10Training & changePRJ-2026-017_5.1_v1.pdfApprovedDeliverable
- 017-D11Go-live & handoverPRJ-2026-017_5.2_v1.pdfIn reviewDeliverable