Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-017At risk5ClosureWaterfall

Correspondence & Document Management System (DMS)

Add to watchlist

Automated correspondence, document management and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 14.2M split into spent, committed and left, with the estimate at completion

EAC SAR 14.2M
Revised request SAR 14.2M
  • Actual spendSAR 13.5M
  • Committed, not spentSAR 410K
  • Allotted, uncommittedSAR 0
  • Contingency availableSAR 426K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 12.2M
Original budgetwhen the first baseline was approved
SAR 14.2M
Approved budgetafter approved change requests
SAR 14.2M
Current budgetavailable to spend now
SAR 14.2M
Revised budgetif the pending changes are approved
SAR 14.2M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 13.9M
Contracts1 active contract
SAR 11.6M
Purchase orders⁦2⁩ orders
SAR 2.3M
Remaining budgetapproved less actual
SAR 710K

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 13.5M
Accrualswork done, not yet invoiced
SAR 540K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 14.2M
ContingencySAR 284K drawn of SAR 710K
SAR 426K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 12.2M
ApprovedSAR 14.2M
Estimate at completionSAR 14.2M
Approved is SAR 2M (⁦16.4%⁩) above the estimate
The estimate at completion is SAR 2M (⁦16.4%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-11-05⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61017
  • WBS elements⁦5⁩ elements · P-2026-017.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦13⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 284K drawn of SAR 710K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 284K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance1.101.141.141.14⁦−0.03⁩
2Analysis & design2.342.412.412.41⁦−0.07⁩
3Build5.515.685.685.68⁦−0.17⁩
4Testing & acceptance2.752.842.842.84⁦−0.09⁩
5Launch & handover2.071.831.421.91⁦+0.15⁩
Unallocated contingency0.430.000.000.21⁦+0.21⁩
Total14.2013.9013.4914.20⁦+0.00⁩

Budget split

WBS

SAR 14.2M

Budget

  • Management & governanceSAR 1.1M⁦8%⁩
  • Analysis & designSAR 2.3M⁦16%⁩
  • BuildSAR 5.5M⁦39%⁩
  • Testing & acceptanceSAR 2.8M⁦19%⁩
  • Launch & handoverSAR 2.1M⁦15%⁩
  • Unallocated contingencySAR 426K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-02-07⁩+130

SPI(t) ⁦0.83⁩ against the approved finish ⁦2026-09-30⁩

Planned valuePV
SAR 14.2M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 13.5M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 13.5M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 14.2M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.71⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.95
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 14.2M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 710K
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 14.2M
  • If the rest goes to planSAR 14.2M
  • At cost and schedule performanceSAR 14.2M
  • The PM’s bottom-up estimateSAR 14.2M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 14.2M

Variance at completion: ⁦+0.00⁩ SAR M

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close