PRJ-2026-017At risk5ClosureWaterfall
Correspondence & Document Management System (DMS)
Add to watchlistAutomated correspondence, document management and e-archiving, linked to the government communications network.
Project managerDana S. Al-SalehProject sponsorSarah A. Al-QarniProgrammeEnterprise Systems & Government Integration Programme
Budget (BAC)
SAR 14.2M
Actual cost
SAR 13.5M
95% of budget
Progress
95%Awaiting acceptance 5%
Estimate at completion
SAR 14.2M
SPI · CPI
0.95Schedule performance index · 0.951.00Cost performance index · 1.00
Forecast finish
2026-11-15
46 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
No update cards for this project — they start with execution.