PRJ-2026-017At risk5ClosureWaterfall

Correspondence & Document Management System (DMS)

Add to watchlist

Automated correspondence, document management and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Team & roles

1 member, about ⁦0.3⁩ full-time equivalents

Leadership

1 member

  • Dana S. Al-SalehProject manager⁦25%⁩Allocated ⁦120%⁩ across all projectsA

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦3⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Sarah A. Al-QarniManage closelyMunirah A. Al-KhalidiManage closelyProject Management Office (PMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedIntegrated Business Systems Co.Manage closely

Interest

Project sponsor

Sarah A. Al-Qarni

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-10-16⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Sarah A. Al-QarniProject sponsorDecisions and fundingSupportiveLeadingDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa⁦2026-10-16⁩
Munirah A. Al-KhalidiProject ownerAccepts deliverables, owns benefitsLeadingDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa⁦2026-10-19⁩
Project Management Office (PMO)GovernanceCompliance and data qualitySupportiveDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa⁦2026-10-13⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@sca.sa⁦2026-10-10⁩
Integrated Business Systems Co.Main vendorDelivers the contracted workLeadingDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa⁦2026-10-20⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa⁦2026-09-22⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingDana S. Al-Saleh⁦2026-11-11⁩
  • Project ownerDeliverable status and acceptance datesFortnightlyEmailDana S. Al-Saleh⁦2026-10-30⁩
  • PMOData and indicator updatesWeeklyDashboardDana S. Al-Saleh⁦2026-10-27⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterDana S. Al-SalehAt launch

Coming up

By date

  1. 272026-10PMODashboard · Weekly
  2. 302026-10Project ownerEmail · Fortnightly
  3. 112026-11Project sponsorMeeting · Monthly