PRJ-2026-017At risk5ClosureWaterfall

Correspondence & Document Management System (DMS)

Add to watchlist

Automated correspondence, document management and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

Automated correspondence, document management and e-archiving, linked to the government communications network.

In scope

  • Automated correspondence, document management and e-archiving, linked to the government communications network.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-02-18⁩

    Baseline approved at the planning gate

    Budget14.2MFinish⁦2026-09-30⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional1
  • Technical2
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦33%⁩

2/6 · test result is a pass

Accepted

⁦33%⁩

2/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-017-01One system for the proceduresBusinessMustIn progressMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saSB-1
REQ-017-02Historical data migrationTechnicalMustIn progressDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.saSB-1
REQ-017-03Ready operational reportsFunctionalMustApprovedMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saSB-1
REQ-017-04ERP integrationTechnicalCouldApprovedDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.saSB-1
REQ-017-05Data classificationRegulatoryShouldIn progressMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saSB-1
REQ-017-06Identity and access managementSecurityShouldIn progressDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.