Correspondence & Document Management System (DMS)
Add to watchlistAutomated correspondence, document management and e-archiving, linked to the government communications network.
Budget (BAC)
Actual cost
95% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
46 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-06-07 | 2025-06-27 | +20 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-09-21 | 2025-10-27 | +36 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-01 | 2026-04-28 | +58 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-06-15 | 2026-08-28 | +74 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-09-30 | 2026-12-24 | +85 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | Late | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
95%Awaiting acceptance
5%Not handed in
0%Deliverable flow
Display options
| Project plan & baseline017-D1 | 4% | CRT-017-01 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | Munirah A. Al-Khalidi | 2025-04-14 | V1 | 3 of 3 |
| Monitoring & reporting017-D2 | 4% | CRT-017-02 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.sa | Munirah A. Al-Khalidi | 2025-06-07 | V1 | 3 of 3 |
| Business requirements017-D3 | 9% | CRT-017-03 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.sa | Munirah A. Al-Khalidi | 2025-07-30 | V1 | 3 of 3 |
| Solution design017-D4 | 9% | CRT-017-04 | Approved | Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.sa | Munirah A. Al-Khalidi | 2025-09-21 | V1 | 3 of 3 |
| Release 1017-D5 | 14% | CRT-017-05 | Approved | Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.sa | Munirah A. Al-Khalidi | 2025-11-14 | V1 | 3 of 3 |
| Release 2017-D6 | 14% | CRT-017-06 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | Munirah A. Al-Khalidi | 2026-01-06 | V1 | 3 of 3 |
| Integrations017-D7 | 13% | CRT-017-07 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.sa | Munirah A. Al-Khalidi | 2026-03-01 | V1 | 3 of 3 |
| System testing017-D8 | 10% | CRT-017-08 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa | Munirah A. Al-Khalidi | 2026-04-23 | V1 | 3 of 3 |
| User acceptance testing017-D9 | 10% | CRT-017-09 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.sa | Munirah A. Al-Khalidi | 2026-06-15 | V1 | 3 of 3 |
| Training & change017-D10 | 8% | CRT-017-10 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.sa | Munirah A. Al-Khalidi | 2026-08-08 | V1 | 3 of 3 |
| Go-live & handover017-D11 | 5% | — | Submitted | Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.sa | Munirah A. Al-Khalidi | 2026-09-30 | V1 | 1 of 3 |
| Total · 11 | 100% |