Certificate ⁦1⁩ — April 2024

SCA headquarters, Riyadh — construction

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
1
Date
⁦2024-05-16⁩
Hijri
8 Dhuʻl-Qiʻdah 1445 AH
Reference
PAY-2024-011-01

Interim payment certificate no. (⁦1⁩)

For the work of April 2024

Contract number
SCA/2024/011
Etimad reference
2401780147
Contract
SCA headquarters, Riyadh — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
SCA Headquarters, Riyadh
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
1,020,000,000
Current contract value
1,058,500,000including variations of SAR 38.5M
Linked milestone
Site handover & mobilisation · MS-G1 Project plan approved

Certificate summary (SAR)

1Total value of work completed to date6,740,000
2Less: previous certificates0
3Value of work in this certificate6,740,000
4Less: retention (⁦10%⁩)(674,000)
5Less: advance payment recovery (⁦10%⁩)(674,000)
6Less: delay and breach penalties0
7Total deductions(1,348,000)
8Net before VAT5,392,000
9Add: value added tax (15%)808,800
10Net amount payable to the contractor6,200,800

Amount in words: Six million two hundred thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 674K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation74,095,00001,090,0001,090,000⁦1%⁩
Earthworks & foundations190,530,00001,698,0001,698,000⁦1%⁩
Concrete & structural works328,135,00002,298,0002,298,000⁦1%⁩
Mechanical, electrical & plumbing254,040,00001,132,0001,132,000⁦0%⁩
Finishes & external works158,775,0000455,000455,000⁦0%⁩
Testing & commissioning52,925,000067,00067,000⁦0%⁩
Total1,058,500,00006,740,0006,740,000⁦1%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2024-05-16⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-05-18⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2024-05-21⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-05-24⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-05-27⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-05-16⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2024-05-18⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2024-05-21⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects

    Took 3 days

  4. Payment order prepared⁦2024-05-24⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-05-27⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneSite handover & mobilisationDone · ⁦2024-06-11⁩
  2. Project milestoneMS-G1Project plan approvedMilestone approved ⁦2025-05-27⁩1 evidence file

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

27 May 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-05-27 13:00

24 May 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-05-24 13:00

21 May 2024

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2024-05-21 13:00

18 May 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2024-05-18 13:00

16 May 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-05-16 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close