Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 12
- Date
- 2025-05-08
- Hijri
- 10 Dhuʻl-Qiʻdah 1446 AH
- Reference
- PAY-2024-011-12
Interim payment certificate no. (12)
For the work of April 2025
- Contract number
- SCA/2024/011
- Etimad reference
- 2401780147
- Contract
- SCA headquarters, Riyadh — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- SCA Headquarters, Riyadh
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 1,020,000,000
- Current contract value
- 1,058,500,000including variations of SAR 38.5M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 188,230,000 |
| 2 | Less: previous certificates | (165,930,000) |
| 3 | Value of work in this certificate | 22,300,000 |
| 4 | Less: retention (10%) | (2,230,000) |
| 5 | Less: advance payment recovery (10%) | (2,230,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (4,460,000) |
| 8 | Net before VAT | 17,840,000 |
| 9 | Add: value added tax (15%) | 2,676,000 |
| 10 | Net amount payable to the contractor | 20,516,000 |
Amount in words: Twenty million five hundred sixteen thousand Saudi riyals only
Retention held up to this certificate: SAR 18.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 74,095,000 | 26,971,000 | 3,428,000 | 30,399,000 | 41% |
| Earthworks & foundations | 190,530,000 | 42,014,000 | 5,420,000 | 47,434,000 | 25% |
| Concrete & structural works | 328,135,000 | 56,562,000 | 7,624,000 | 64,186,000 | 20% |
| Mechanical, electrical & plumbing | 254,040,000 | 27,677,000 | 3,946,000 | 31,623,000 | 12% |
| Finishes & external works | 158,775,000 | 11,073,000 | 1,633,000 | 12,706,000 | 8% |
| Testing & commissioning | 52,925,000 | 1,633,000 | 249,000 | 1,882,000 | 4% |
| Total | 1,058,500,000 | 165,930,000 | 22,300,000 | 188,230,000 | 18% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani