Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 17
- Date
- 2025-10-18
- Hijri
- 26 Rabiʻ II 1447 AH
- Reference
- PAY-2024-011-17
Interim payment certificate no. (17)
For the work of September 2025
- Contract number
- SCA/2024/011
- Etimad reference
- 2401780147
- Contract
- SCA headquarters, Riyadh — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- SCA Headquarters, Riyadh
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 1,020,000,000
- Current contract value
- 1,058,500,000including variations of SAR 38.5M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 295,690,000 |
| 2 | Less: previous certificates | (276,730,000) |
| 3 | Value of work in this certificate | 18,960,000 |
| 4 | Less: retention (10%) | (1,896,000) |
| 5 | Less: advance payment recovery (10%) | (1,896,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (3,792,000) |
| 8 | Net before VAT | 15,168,000 |
| 9 | Add: value added tax (15%) | 2,275,200 |
| 10 | Net amount payable to the contractor | 17,443,200 |
Amount in words: Seventeen million four hundred forty-three thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 29.6M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 74,095,000 | 44,944,000 | 2,810,000 | 47,754,000 | 64% |
| Earthworks & foundations | 190,530,000 | 70,026,000 | 4,488,000 | 74,514,000 | 39% |
| Concrete & structural works | 328,135,000 | 94,336,000 | 6,494,000 | 100,830,000 | 31% |
| Mechanical, electrical & plumbing | 254,040,000 | 46,200,000 | 3,476,000 | 49,676,000 | 20% |
| Finishes & external works | 158,775,000 | 18,493,000 | 1,466,000 | 19,959,000 | 13% |
| Testing & commissioning | 52,925,000 | 2,731,000 | 226,000 | 2,957,000 | 6% |
| Total | 1,058,500,000 | 276,730,000 | 18,960,000 | 295,690,000 | 28% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani