SCA strategy refresh — draft

SCA Strategy Refresh & Execution Plans

⁦1⁩. Executive summary

This report gives the position of SCA Strategy Refresh & Execution Plans to date: ⁦70%⁩ complete against ⁦68%⁩ planned, SPI ⁦1.03⁩, CPI ⁦1.00⁩, and an estimate at completion of SAR ⁦3.2M⁩.

Project
SCA Strategy Refresh & Execution Plans (⁦PRJ-2026-028⁩)
Project manager
Abeer H. Al-Shamrani
Budget
SAR ⁦3.2M⁩
Progress
⁦70%⁩ actual against ⁦68%⁩ planned
Forecast finish
⁦2026-12-15⁩

⁦2⁩. Key findings

  • All planned milestones of the period met except one deferred
  • Actual spend rose in line with the work done
  • Three high risks under treatment, each with a named owner

⁦3⁩. Recommendations & decisions needed

  • Approve the proposed treatment of the high risks
  • Track the open findings with the vendor weekly

Prepared by

Abeer H. Al-Shamrani
Issued from Munjaz — valid only once approved electronically1 / 1