Saudi Contractors AuthorityMunjaz11My actionsNotifications

Portfolio executive report — September 2026

Portfolio executive reportConfidential

Saudi Contractors Authority · September 2026

Shown by your permissionsProject Management Office: 36 projects — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Portfolio executive report

Portfolio executive report — September 2026

Saudi Contractors Authority

Period
September 2026
Generated
5 October 202624 Rabiʻ II 1448 AH
Submitted to
The Secretary-General and senior management
Owner
Dr. Noura M. Al-Otaibi

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-01 · page ⁦1⁩ of ⁦5⁩Confidential
Portfolio executive report — September 2026Saudi Contractors Authority

Executive summary

Written by Copilot from system data — review before sending

The scope holds 36 projects with a budget of SAR 5.15B: 18 on track and 6 red or critical. Weighted progress is 52% against 57% planned, spend SAR 2.41B, and EAC SAR 5.56B (SAR 407.7M over).

12 projects are more than a month behind baseline; the worst: SCA Academy Campus, Riyadh (152 days), Al-Khobar Branch — Rehabilitation & Extension (126 days), Jeddah Branch & Qualification Centre (95 days).

18 high risks are open with SAR 403.4M of exposure; the decisions needed centre on contractor distress and the large change requests.

Key figures

Projects
36
Budget
SAR 5.2B
Spent
SAR 2.4B
EAC
SAR 5.6B
Progress
⁦52%⁩ / ⁦57%⁩
SPI
0.85
CPI
0.93
High risks
18

Project health mix

  • On track 18
  • At risk 10
  • Off track 4
  • Critical 2
  • On hold 2
Munjaz · RPT-01 · page ⁦2⁩ of ⁦5⁩Confidential
Portfolio executive report — September 2026Saudi Contractors Authority

Budget and EAC by portfolio

Budget and EAC by portfolio
  • Budget
  • EAC
Budget and EAC by portfolio
CategoryBudgetEAC
Digital Services & Platforms PortfolioSAR 180.3MSAR 183.9M
Academy & Qualification Centres PortfolioSAR 1.3BSAR 1.5B
Technology & Enterprise Systems PortfolioSAR 352.7MSAR 376M
Building Rehabilitation & Sustainability PortfolioSAR 650MSAR 726M
Headquarters & Regional Centres PortfolioSAR 2.6BSAR 2.8B
Institutional Excellence & Governance PortfolioSAR 30.5MSAR 30.5M

Monthly spend 2026

Monthly spend 2026
  • Actual
  • Planned
  • Forecast
Monthly spend 2026
PeriodActualPlanned
JanSAR 79MSAR 86M
FebSAR 84MSAR 92M
MarSAR 101MSAR 118M
AprSAR 109MSAR 124M
MaySAR 117MSAR 131M
JunSAR 113MSAR 128M
JulSAR 96MSAR 112M
AugSAR 104MSAR 121M
SepSAR 115MSAR 137M
OctSAR 121MSAR 142M
Nov (Forecast)SAR 132MSAR 148M
Dec (Forecast)SAR 158MSAR 171M
Munjaz · RPT-01 · page ⁦3⁩ of ⁦5⁩Confidential
Portfolio executive report — September 2026Saudi Contractors Authority

Projects with the most at stake

ProjectSectorBudgetProgressHealth
SCA Headquarters, RiyadhSupportSAR 1.2B⁦42%⁩Off track
SCA Academy Campus, RiyadhQualificationSAR 640M⁦57%⁩Critical
Asir Vocational Qualification CentreSupportSAR 520M⁦2%⁩On track
Al-Khobar Branch — Rehabilitation & ExtensionSupportSAR 412M⁦68%⁩Critical
Qassim Vocational Qualification CentreSupportSAR 345M⁦44%⁩Off track
Jeddah Branch & Qualification CentreQualificationSAR 286M⁦39%⁩Off track
Arar Vocational Qualification CentreQualificationSAR 238M⁦33%⁩At risk
Wadi Al-Dawasir Vocational Qualification CentreQualificationSAR 210M⁦2%⁩On hold
Hail Vocational Qualification CentreQualificationSAR 158M⁦52%⁩At risk
SCA Backup Data CentreDigitalSAR 148M⁦72%⁩At risk
Secure Enterprise NetworkDigitalSAR 132M⁦55%⁩At risk
Unified Operations Centre for Centres & PlatformsDigitalSAR 110M⁦0%⁩On track

The largest ⁦12⁩ of ⁦36⁩ by budget — the full table is in the Excel file

Munjaz · RPT-01 · page ⁦4⁩ of ⁦5⁩Confidential
Portfolio executive report — September 2026Saudi Contractors Authority

Highest-exposure risks

RiskScoreExposure
Main contractor cash-flow distress and unpaid subcontractorsAl-Khobar Branch — Rehabilitation & Extension25SAR 36M
Steel and concrete price rises driving price-adjustment claimsSCA Headquarters, Riyadh20SAR 48M
Contractor financial claims piling up over unapproved variationsSCA Academy Campus, Riyadh20SAR 41M
Late handover of the northern plot and utility diversions in zones 3 and 4SCA Headquarters, Riyadh20SAR 31M
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16Qassim Vocational Qualification Centre20SAR 27M
Late land handover and title deed from the owning entity in Wadi Al-DawasirWadi Al-Dawasir Vocational Qualification Centre20SAR 12M
Ground-improvement costs up after the geotechnical surveyJeddah Branch & Qualification Centre16SAR 22.5M

Decisions needed

  1. 1

    Pay subcontractors directly on the Al-Khobar branch rehabilitation & extension

    The PMO recommends paying directly out of certificate 22 and deducting it from the main contractor’s dues.

  2. 2

    Refer the SCA Academy campus contractor’s claims to arbitration

    Legal recommends referral, with an independent engineer assessing the extension request in parallel.

  3. 3

    Approve the updated corrective plan for Muqawil Release 4

    The Steering Committee recommends conditional approval with a monthly progress review.

  4. 4

    Release SAR 22M of the HQ & regional centres portfolio reserve to speed up the HQ land handover

    Facilities & Premises recommends two tranches tied to site handovers.

Munjaz · RPT-01 · page ⁦5⁩ of ⁦5⁩Confidential
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close