Sector or portfolio report — Digital Services & Platforms Portfolio

Sector or portfolio reportConfidential

Digital Services & Platforms Portfolio · October 2026 — ahead of 3 November

Shown by your permissionsProject Management Office: 7 projects — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Sector or portfolio report

Sector or portfolio report — Digital Services & Platforms Portfolio

Digital Services & Platforms Portfolio

Period
October 2026 — ahead of 3 November
Generated
13 October 20262 Jumada I 1448 AH
Submitted to
The sector head and the Projects Steering Committee
Owner
Faisal A. Al-Shehri

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-03 · page ⁦1⁩ of ⁦5⁩Confidential
Sector or portfolio report — Digital Services & Platforms PortfolioSaudi Contractors Authority

Executive summary

Written by Copilot from system data — review before sending

The Digital Services portfolio holds 7 projects with an approved SAR 190M; SAR 124.6M is committed and SAR 98.6M spent. EAC is SAR 183.9M — within budget by SAR 6.1M. Five projects are green, two amber, none red.

The main concern is Muqawil Release 4 (SAR 86.4M, 45% of the portfolio): 42 days behind baseline with a 74% chance of further slippage within 45 days. Its strategic effect shows in satisfaction with digital services stuck at 74% against an 85% target. The rest is on track: Wifaq is 91% done and the mobile app runs at SPI 1.02.

Three decisions are asked of the committee: (1) move membership transfer & record merge to wave 2 rather than adding it now (+21 days, SAR 1.85M); (2) approve the internal resource reallocation to integration; (3) send the vendor a formal letter on replacing its integration engineers.

Key figures

Projects
7
Budget
SAR 180.3M
Spent
SAR 98.6M
EAC
SAR 183.9M
Progress
⁦61%⁩ / ⁦64%⁩
SPI
0.92
CPI
0.98
High risks
2

Project health mix

  • On track 5
  • At risk 2
Munjaz · RPT-03 · page ⁦2⁩ of ⁦5⁩Confidential
Sector or portfolio report — Digital Services & Platforms PortfolioSaudi Contractors Authority

Progress by sector

Progress by sector
Progress by sector
CategoryProgress
Strategy & Excellence⁦0%⁩
Regulation⁦61%⁩
Services⁦64%⁩
Digital⁦58%⁩

Projects and their weights

ProjectWeightProgress
Muqawil Platform — Release 4⁦21.8%⁩⁦58%⁩
Contracting Sector Information Centre & Data Governance⁦17.3%⁩⁦62%⁩
Project Tracking Platform — National Phase⁦16.3%⁩⁦1%⁩
Wifaq Dispute Settlement Platform — Release 2⁦15.6%⁩⁦91%⁩
Muqawil Mobile App — Release 3⁦15.6%⁩⁦64%⁩
Electronic Model Contracts⁦13.4%⁩⁦100%⁩
Future Projects Forum 2027—⁦0%⁩

Relative weight in the portfolio: the project’s share of its portfolio’s budget, adjusted by its priority score; each portfolio’s weights add to 100%; proposed and cancelled projects carry none.

Munjaz · RPT-03 · page ⁦3⁩ of ⁦5⁩Confidential
Sector or portfolio report — Digital Services & Platforms PortfolioSaudi Contractors Authority

Projects with the most at stake

ProjectWeightProgressSlipHealth
Muqawil Platform — Release 4⁦21.8%⁩⁦58%⁩42 daysAt risk
Project Tracking Platform — National Phase⁦16.3%⁩⁦1%⁩—On track
Contracting Sector Information Centre & Data Governance⁦17.3%⁩⁦62%⁩18 daysAt risk
Wifaq Dispute Settlement Platform — Release 2⁦15.6%⁩⁦91%⁩—On track
Muqawil Mobile App — Release 3⁦15.6%⁩⁦64%⁩—On track
Electronic Model Contracts⁦13.4%⁩⁦100%⁩20 daysOn track
Future Projects Forum 2027—⁦0%⁩—On track
Munjaz · RPT-03 · page ⁦4⁩ of ⁦5⁩Confidential
Sector or portfolio report — Digital Services & Platforms PortfolioSaudi Contractors Authority

Highest-exposure risks

RiskScoreExposure
Nafath and Government Service Bus integration interfaces not ready on timeMuqawil Platform — Release 416SAR 2.4M
Shortage of integration and back-end engineers on the vendor teamMuqawil Platform — Release 416SAR 1.9M
Late sign-off of membership-service requirements by the owning departmentsMuqawil Platform — Release 412SAR 1.2M
Possible critical findings in the pre-launch penetration testMuqawil Platform — Release 412SAR 600K
Incomplete migration of membership and open-request data from legacy systemsMuqawil Platform — Release 49SAR 750K
Too few accredited data owners in the sectors and departmentsContracting Sector Information Centre & Data Governance9SAR 650K
Mobile-app team competing with the platform for the same peopleMuqawil Platform — Release 49SAR 520K

Decisions needed

  1. 1

    Approve the updated corrective plan for Muqawil Release 4

    The Steering Committee recommends conditional approval with a monthly progress review.

  2. 2

    Approve the October Steering Committee minutes

    Reviewed by the committee secretary; no open comments.

Munjaz · RPT-03 · page ⁦5⁩ of ⁦5⁩Confidential