Saudi Contractors AuthorityMunjaz11My actionsNotifications

Certificate ⁦1⁩ — February 2024

Engineering supervision — Al-Khobar branch

Kingdom of Saudi Arabia

Saudi Contractors Authority

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
1
Date
⁦2024-03-17⁩
Hijri
7 Ramadan 1445 AH
Reference
PAY-2024-005-01

Interim payment certificate no. (⁦1⁩)

For the work of February 2024

Contract number
SCA/2024/005
Etimad reference
2401360069
Contract
Engineering supervision — Al-Khobar branch
Contractor
Ma’alem International Project Management
Contractor VAT number
340304288130003
Project
Al-Khobar Branch — Rehabilitation & Extension
Contract period
⁦2024-02-01⁩ — ⁦2027-03-31⁩
Original contract value
14,600,000
Current contract value
14,600,000
Linked milestone
Supervision team mobilised · MS-G1 Project plan approved

Certificate summary (SAR)

1Total value of work completed to date220,000
2Less: previous certificates0
3Value of work in this certificate220,000
4Less: retention (⁦5%⁩)(11,000)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(11,000)
8Net before VAT209,000
9Add: value added tax (15%)31,350
10Net amount payable to the contractor240,350

Amount in words: Two hundred forty thousand three hundred fifty Saudi riyals only

Retention held up to this certificate: SAR 11K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Resident engineering staff9,052,0000137,000137,000⁦2%⁩
Visiting specialists2,628,000040,00040,000⁦2%⁩
Laboratory & testing1,752,000024,00024,000⁦1%⁩
Reporting & technical office1,168,000019,00019,000⁦2%⁩
Total14,600,0000220,000220,000⁦2%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. James Harlow

Harlow⁦2024-03-17⁩

Supervising engineer

Haifa S. Al-Ruwaili

Al-Ruwaili⁦2024-03-19⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2024-03-22⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-03-25⁩

Authority holder

Munirah A. Al-Khalidi

Al-Khalidi⁦2024-03-28⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-03-17⁩

    Eng. James Harlow

  2. Engineer verifies quantities⁦2024-03-19⁩

    Haifa S. Al-Ruwaili · Senior Financial Analyst

    Took 2 days

  3. Project manager certifies⁦2024-03-22⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2024-03-25⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-03-28⁩

    Munirah A. Al-Khalidi · Director General, Finance & Procurement

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneSupervision team mobilisedDone · ⁦2024-03-18⁩
  2. Project milestoneMS-G1Project plan approvedMilestone approved ⁦2024-11-17⁩1 evidence file

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Munirah A. Al-Khalidi
  • Whoever verified quantities does not prepare the payment orderHaifa S. Al-Ruwaili → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Munirah A. Al-Khalidi

Certificate history

28 March 2024

  1. Payment: Munirah A. Al-Khalidi signed “Final approval”

    2024-03-28 13:00

25 March 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-03-25 13:00

22 March 2024

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2024-03-22 13:00

19 March 2024

  1. Approval: Haifa S. Al-Ruwaili signed “Engineer verifies quantities”

    2024-03-19 13:00

17 March 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-03-17 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close