SCA/2024/005
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
73% of the current value paid
Paid
10.7Mof a current value of SAR 14.6M
Value of each certificate
The last 14 — gross and net
Approved: 21
Count: 21 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 21September 2026 | 2026-10-06 | 240K | 12K | 0 | 34.2K | 262.2K | Approved | |
| Certificate 20July 2026 | 2026-08-20 | 290K | 14.5K | 0 | 41.3K | 316.8K | Approved | |
| Certificate 19June 2026 | 2026-07-05 | 350K | 17.5K | 0 | 49.9K | 382.4K | Approved | |
| Certificate 18April 2026 | 2026-05-19 | 480K | 24K | 0 | 68.4K | 524.4K | Approved | |
| Certificate 17March 2026 | 2026-04-02 | 460K | 23K | 0 | 65.6K | 502.6K | Approved | |
| Certificate 16January 2026 | 2026-02-15 | 560K | 28K | 0 | 79.8K | 611.8K | Approved | |
| Certificate 15December 2025 | 2025-12-30 | 650K | 32.5K | 0 | 92.6K | 710.1K | Approved | |
| Certificate 14October 2025 | 2025-11-13 | 580K | 29K | 0 | 82.7K | 633.7K | Approved | |
| Certificate 13September 2025 | 2025-09-28 | 720K | 36K | 0 | 102.6K | 786.6K | Approved | |
| Certificate 12July 2025 | 2025-08-12 | 700K | 35K | 0 | 99.8K | 764.8K | Approved | |
| Certificate 11June 2025 | 2025-06-27 | 630K | 31.5K | 0 | 89.8K | 688.3K | Approved | |
| Certificate 10April 2025 | 2025-05-11 | 760K | 38K | 0 | 108.3K | 830.3K | Approved | |
| Certificate 9March 2025 | 2025-03-25 | 640K | 32K | 0 | 91.2K | 699.2K | Approved | |
| Certificate 8January 2025 | 2025-02-07 | 620K | 31K | 0 | 88.4K | 677.4K | Approved | |
| Certificate 7December 2024 | 2024-12-22 | 670K | 33.5K | 0 | 95.5K | 732K | Approved | |
| Certificate 6October 2024 | 2024-11-05 | 510K | 25.5K | 0 | 72.7K | 557.2K | Approved | |
| Certificate 5August 2024 | 2024-09-20 | 510K | 25.5K | 0 | 72.7K | 557.2K | Approved | |
| Certificate 4July 2024 | 2024-08-04 | 460K | 23K | 0 | 65.6K | 502.6K | Approved | |
| Certificate 3May 2024 | 2024-06-18 | 340K | 17K | 0 | 48.5K | 371.5K | Approved | |
| Certificate 2April 2024 | 2024-05-03 | 310K | 15.5K | 0 | 44.2K | 338.7K | Approved | |
| Certificate 1February 2024 | 2024-03-17 | 220K | 11K | 0 | 31.4K | 240.4K | Approved |