Kingdom of Saudi Arabia
Saudi Contractors Authority
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 8
- Date
- 2024-12-29
- Hijri
- 28 Jumada II 1446 AH
- Reference
- PAY-2024-011-08
Interim payment certificate no. (8)
For the work of December 2024
- Contract number
- SCA/2024/011
- Etimad reference
- 2401780147
- Contract
- SCA headquarters, Riyadh — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- SCA Headquarters, Riyadh
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 1,020,000,000
- Current contract value
- 1,058,500,000including variations of SAR 38.5M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 104,740,000 |
| 2 | Less: previous certificates | (86,810,000) |
| 3 | Value of work in this certificate | 17,930,000 |
| 4 | Less: retention (10%) | (1,793,000) |
| 5 | Less: advance payment recovery (10%) | (1,793,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (3,586,000) |
| 8 | Net before VAT | 14,344,000 |
| 9 | Add: value added tax (15%) | 2,151,600 |
| 10 | Net amount payable to the contractor | 16,495,600 |
Amount in words: Sixteen million four hundred ninety-five thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 10.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 74,095,000 | 14,094,000 | 2,823,000 | 16,917,000 | 23% |
| Earthworks & foundations | 190,530,000 | 21,960,000 | 4,434,000 | 26,394,000 | 14% |
| Concrete & structural works | 328,135,000 | 29,594,000 | 6,122,000 | 35,716,000 | 11% |
| Mechanical, electrical & plumbing | 254,040,000 | 14,500,000 | 3,096,000 | 17,596,000 | 7% |
| Finishes & external works | 158,775,000 | 5,806,000 | 1,264,000 | 7,070,000 | 4% |
| Testing & commissioning | 52,925,000 | 856,000 | 191,000 | 1,047,000 | 2% |
| Total | 1,058,500,000 | 86,810,000 | 17,930,000 | 104,740,000 | 10% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani